Skip to content

Transport of Silica Arena: HDPE vs Pexgol

Test Installation for Transporting Silica Sand.

Case Study Nº

90

Customer

Covia Corp
Mexico

|

2019

Working Conditions

Pneumatic transport at 6 bar

Pexgol Pipes

Pexgol Elbow 90° 225 mm (8”), Class 15 | Pexgol Flange Coupler 225 mm (8”)

Application

Transport of Silica Arena

Lenght

Categories

Test Installation for Transporting Silica Sand.

The Challenge

Covia Corp, a leading company in the manufacture and sale of industrial minerals in Mexico, required to pneumatic transport silica sand at 6 bar (with 50% solids). Initially they worked with 225mm (8”) HDPE pipes that suffered from high levels of wear at the elbows due to abrasion of the material it was carrying.

Pexgol Solution

The client decided to replace one of the HDPE elbows with a Pexgol 90° 225 mm (8”) class 15 and test it for 3 months.
HDPE elbows generally lasted up to a month and a half of work. The Pexgol elbow had to at least double the operating time to pass the test.

After 3 months of testing it was shown that Pexgol exceeded expectations. It’s been more than a year and the elbows continue to function without problems.

Only torque wrenches were used for the installation.

Related Case Studies

Transport of high corrosive material from the thickeners to the neutralization plant

Corrosive Material Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2015
Pexgol’s chemical resistance and flexibility outperform HDPE in demanding leach pad operations.

Greater Efficiency and Safety in Leaching with Pexgol Pipes

Barrick Gold Corp.
Argentina

 | 

2025
Dry Gas Line for Pump Activation.

Dry Gas Transportation

ExxonMobil
Argentina

 | 

2020
Replacement of Steel Pipes with Pexgol for Testing Centrifugal Pumps.

Pexgol for Centrifugal Pump Test

Flowserve
Argentina

 | 

2022
Installation of 1000 Meters of PE-X Pipe for an Underground Mine.

Mining Drainage Lines

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019
Installation of Pexgol Pipesf for the Drainage of an Underground Mine.

High Pressure Drain in Underground Mine

Ojos del Salado Mine – Lundin Mining
Chile

 | 

2018