Skip to content

Replacement of Steel Pipes for PE-X

Replacing Steel for PE-X Pipes to Transported Processed Water.

Case Study Nº

105

Customer

Rosebel Gold Mines – IamGold
Suriname

|

2020

Working Conditions

Pressure: 60 PSI | Flow: 70 m3/h | Temperature: 45°C | Fluid: Processed water

Pexgol Pipes

Pexgol 225 mm (8”)

Application

Processed water transportation

Lenght

100 m / 328 ft + elbows + tees + reducers

Categories

Replacing Steel for PE-X Pipes to Transported Processed Water.

The Challenge

At the Rosebel Gold mine they had serious scale problems in the water transport line for the SAG Fees Chute mill.

They generally used steel pipes that ended up becoming encrusted, which resulted in them needing to be cleaned and on many occasions changed in periods of 3 to 5 months. This generated losses in production and a large cost for the maintenance that the steel required. Additionally, in the periods of use, the pumping pressures had to increase since the internal diameter of the pipe was reduced.

Pexgol Solution

The client was aware of the advantages of Pexgol to prevent fouling in lime slurry transport applications and therefore it was decided to proceed with a first section for testing.

With the Pexgol piping system, which has a low internal roughness, long radius elbows and mechanical accessories were supplied that helped ensure that even between the joints there were no interferences.

Today the system has been working for more than 10 months without problems or fouling, which is already a success for the client since its installation is simple and the costs are lower than steel pipes.

The connections were mechanical, it was only necessary to cut the pipe to size and place screws. PE-X is much lighter than steel, so fitting it to the pipe racks was also simple.

Additionally, the plant has Victaulic-type connections on the steel pipes, which made the job simple as Pexgol can also connect with Victaulic.

Related Case Studies

Installation of a Pexgol Line 200 Meters Deep at an Underground Mine

Transport of Compressed Air

Meridian Mine – Faena El Peñón
Chile

 | 

2018
Installation of Buried Pipes to Transport Water on a Mining Road.

Water Transportation on a Mining Road

CODELCO – Andina Mine
Chile

 | 

2019
EMESA Optimizes Formation Water Transportation in Mendoza.

Pexgol’s Solution in Secondary Recovery for EMESA

EMESA
Argentina

 | 

2023
Food Transport Pexgol vs HDPE

Food Transport Pexgol vs HDPE

Marine Farms
Chile

 | 

2017
Vertical Mobile Pexgol Installation on the Rocks for Mine Dewatering.

Mine Dewatering at Low Temperature

Ferrexpo Yeristovo Mining
Ukraine

 | 

2019
The Original Design for a Wastewater Treatment Plant included Stainless Steel Pipes, but after discovering the Superior Capabilities of Pexgol Pipes, the Entire Facility was Switched Over.

New Wastewater Treatment Plant with Pexgol Pipes

Wastewater Treatment Plant
Israel

 | 

2022