Skip to content

Backfill

Cement Slurry Injection to an Underground Mine

Case Study Nº

35

Customer

Aguilar Mine
Argentina

|

2015

Working Conditions

Fluids: Cement 450.2 g; Water 500 ml; Volume 670 cm.; Density 1.4 t/m. Pressure: Temporary pressures up to 33 k/cm2. Height difference: 300 meters.

Pexgol Pipes

Pexgol 110 mm (4”) Class 24 (SDR 7.4).

Application

Backfill

Lenght

1,400 meters.

Categories

Cement Slurry Injection To An Underground Mine

The Challenge

Due to this special circumstances, the client requested Pexgol pipes since they can be provided in 600 meters sections, they are flexible and highly resistant to abrasion and impacts.

The pipe sections were uncoiled hundreds of meters from the installation place, later they were descended with a hydraulic crane.

The end of the pipe was connected with a conical weight used as a guide to help it descend trough the robbins.

The ground was very harsh with sharp rocks, however the pipes were dragged, pulled and descended without problems.

The pipes were practically hanging from the surface of each level on the mine, supported by electro-fusion couplers. Despite the complicated conditions, the installation took only 60 net hours of work.

Pexgol Solution

Pexgol pipes were the optimal solution for this project, because it can be supplied in long lengths coils that makes the whole installation easier.

Pexgol is also known for its stress resistance, Pexgol’s crosslinking piping solution can withstand high amounts of axial and radial stresses, it only stretches up to 2% of its own length and it is capable to hold its own weight plus the water column.

Due to it great flexibility, the coil was uncoiled hundreds of meters away from the installation place, and it was dragged after to the right spot.

In order to descend the pipe through the open cast, it required only chains and a backhoe to hold it. Arcelor Mittal was very satisfied with the installation process, which was simple, and from their point of view, impossible to do it with other type of pipe.

Related Case Studies

High-pressure water transport for the Southern Pit in a copper and zinc mine.

High-pressure fluid transport

Minera Antapaccay
Peru

 | 

2023
Pexgol’s piping system enabled Nexa Resources to revamp their waste management process, significantly reducing environmental impact.

Enhancing Nexa Resource’s Waste Management Using Pexgol Pipes

Nexa Resources
Brazil

 | 

2023
Installation of Pexgol Pipesf for the Drainage of an Underground Mine.

High Pressure Drain in Underground Mine

Ojos del Salado Mine – Lundin Mining
Chile

 | 

2018
Pexgol technology can overcome challenges in shallow well applications, offering an efficient and cost-effective solution for leading companies in the agricultural industry.

Success in Agricultural Desalination: Water Supply Challenges

BerryMex
Mexico

 | 

2019
Pexgol Transforms Tailings Transportation at Minera San Julián.

Minera San Julián Adopts Pexgol to Improve Water Management

Fresnillo plc
Mexico

 | 

2024
Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012