High Pressure Drain in Underground Mine

Installation of Pexgol Pipesf for the Drainage of an Underground Mine.

Case Study Nº

65

Customer

Ojos del Salado Mine – Lundin Mining
Chile

|

2018

Working Conditions

Underground work

Pexgol Pipes

Pexgol 160 mm (6”), Class 24

Application

Dewatering

Lenght

600 m

Categories

Installation of Pexgol Pipesf for the Drainage of an Underground Mine.

The Challenge

The Ojos del Salado mine (Lundin Mining) required the installation of a line for the drainage of high pressure water from the lower mine level, through the vertical ventilation chimney, with a height of 30 meters.

Primarily the client faced time problems on one hand and on the other hand needed the pipeline to be installed in the shortest time possible, without interfering with the mine’s operation.

Pexgol Solution

It was decided to install a 600 m line of Pexgol 160 mm (6″) class 24 pipe for drainage due to its long length supply format, ease of installation, flexibility contributing to easy accommodation into the curves of the mine interior. Furthermore, due to limited installation times operation stops could be avoided.

It took only 2 days to uncoil and assemble the pipe. For reasons of convenience and at the request of the Prevention Department, the pipeline was placed in sections of 150 meters, since it had to be pulled a 5 km long ramp from the mine interior to the installation point.

Under the same conditions when installing HDPE pipeline, it would have taken about 1 week only to prepare the sections before installing them inside the mine and furthermore only shorter sections could have been installed due to the rigidity of the material.

Related Case Studies

Installation of Pexgol Pipes for a Compress Air System.

Compressed Air System

Rav-Gon Printing House
Israel

 | 

2020
An Outdoor Hydrant and Indoor Sprinklers were installed at Guyana Airport

Water Supply & Fire Extinguisher Line

Cheddi Jagan International Airport
Guyana

 | 

2018
Bridging the Gap between Durability and Functionality in Harsh Processing Environments.

Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport

Syncrude
Canada

 | 

2022
Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE.

Pexgol Elbow for Slurry Transport

Antioquia Gold
Colombia

 | 

2022
Pexgol and Fresnillo: Allies in innovative piping solutions for mining.

Safety and durability: The heart of our solutions

Minera Fresnillo
Mexico

 | 

2021
Installation of Pexgol Pipe for Transportation of Mining Tailings.

Tailings Transport with 50% solids

Golden Resource Corp. – Don David Gold Mine
Mexico

 | 

2019