Pulp & Paper Mill

Hot Caustic Line Replacement in Paper Mill

Case Study Nº

51

Customer

Svetlogorskiy Mill
Russia

|

2015

Working Conditions

Non-pressure, high temperature and scrubber water

Pexgol Pipes

Pexgol 160 mm Class 15

Application

Alkali transportation in caustic and regeneration workshop

Lenght

13 m

Categories

Hot Caustic Line Replacement In Paper Mill

The Challenge

At Svetlogorskiy Mill Paper Plant they needed to repair their stainless steel pipes a few times a year, since they were transporting alkali at very high temperature.
The main challenge for the line was the sedimentation issues.

Pexgol Solution

The client decided to replace the stainless steel pipes with Pexgol pipes. Thanks to it smooth inner surface, sedimentation is not a problem and as a consequence requires less maintenance.
The line has been installed since 2015 and it stills shows amazing results.

Related Case Studies

Transportation of brackish water to the main pumping station

Water Lines – Harsh Conditions

Dead Sea Works
Israel

 | 

1993
Replacing HDPE pipes with Pexgol allowed Vale to simplify operations, eliminate auxiliary equipment, and achieve a permanent installation under extreme conditions.

Comprehensive Redesign of the PumpingSystem with Pexgol at the Sossego Mine

Vale
Brazil

 | 

2024
Water line feed from wells to mine

Mine Dewatering – High Pressure Conditions

Antofagasta Minerals, Michilla Mine
Chile

 | 

2011
Pexgol’s Role in Enhancing Guaymas Protein’s Operations.

Transition to Corrosion-Free Diesel Delivery Systems

Guaymas Protein
Mexico

 | 

2023
Installation of Pexgol Pipe to Transport Fiber Optic Cables.

Fiber Optic Cables Through a Vertical Shaft

Sinohydro
Israel

 | 

2021
Pexgol’s chemical resistance and flexibility outperform HDPE in demanding leach pad operations.

Greater Efficiency and Safety in Leaching with Pexgol Pipes

Barrick Gold Corp.
Argentina

 | 

2025