Fresh Water Line Optimization in an Oil Field in Argentina

Greater operational efficiency with fewer joints and fast implementation.

Case Study Nº

193

Customer

Phoenix Global Resources
Argentina

|

2025

Working Conditions

Temperature: 20 °C / 68°F | Pressure: 12 kg/cm² | Fluid components: Fresh water

Pexgol Pipes

Pexgol 110 mm, Class 24

Application

Fresh water transport

Lenght

1260 m / 4133 ft

Categories

Fresh Water Line Optimization in an Oil Field in Argentina

The Challenge

Phoenix Global Resources, an independent company focused on hydrocarbon exploration and production in Argentina, required the implementation of a new pipeline to transport fresh water from an intake point to its Central Processing Facility (CPF).

The main challenge of the project was not only the fluid conveyance itself, but also the execution conditions: it was essential to minimize installation time, optimize operational costs, and significantly reduce the number of joints along the pipeline route.

In this context, traditional solutions implied longer installation times, a greater need for fittings, and an increase in potential failure points. Additionally, the operation required a reliable solution capable of working at a pressure of 12 kg/cm² with a constant flow rate, ensuring continuity in the water supply for production processes.

The Solution

For this project, a 110 mm (Class 24) Pexgol pipe was implemented, with a total length of 1,260 meters, designed for fresh water transport under demanding operating conditions.

The selection of Pexgol made it possible to drastically reduce the number of joints thanks to its supply in long continuous lengths, improving system reliability and reducing installation time.

Project execution was completed in just 3 days, including trench installation, jointing through electrofusion and mechanical connections, and the final hydrostatic test.

A key aspect was the technical support provided during installation, as the contractor had no prior experience handling Pexgol pipes. This support ensured proper execution and maximized the system’s benefits from the outset.

Thanks to its flexibility, low weight, and ease of handling, the Pexgol solution enabled a fast, safe, and efficient installation, meeting the client’s objectives in terms of time, costs, and operational reliability.

Related Case Studies

A flexible and durable solution designed to adapt to pit benches, operate outdoors, and minimize connection work in difficult-to-access areas.

Safe Installation of a 355 mm Mine DewateringLine

MMG
Perú

 | 

2024
Pan American Energy implements an efficient and sustainable solution for brine transportation.

Fast and Safe Brine Transport in the Salar de Hombre Muerto

Lithos (PAE)
Argentina

 | 

2024
How Pexgol piping improved the fire network system infrastructure in a paint manufacturing plant.

Pexgol Piping for Fire Network System Expansion

Wall
Argentina

 | 

2023
The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Improvement in Brine Management through Pexgol Piping

Sales de Jujuy
Argentina

 | 

2023
Mining Effluent Transportation in Cuba.

Pexgol Optimizes Tailings Management at Sherritt’s Moa Nickel Mine

Sherritt
Cuba

 | 

2020
Scale build up reduction - highly concentrated lime solution

Process Water – Brine Transportation

SQM Nueva Victoria-Iquique
Chile

 | 

2010