Case Study Nº

151

Customer

Anglo American Perú
Peru

|

2023

Working Conditions

Temperature: 15°-20°C (59° – 68°F) | Flow: 450 m^3/h | Pressure: 22 bar | Fluid components: Tailings with high percentage of solids 70%CW

Pexgol Pipes

Pexgol 14″, SDR 11

Application

Tailings transportation in copper mining

Lenght

180 m / 590 ft

Categories

Navigating extreme conditions with Pexgol’s PE-X pipes

The Challenge

In 2023, Anglo American Peru, a global mining leader, faced a significant challenge at its Quellaveco mine. The existing HDPE pipeline, designed for transporting copper tailings with high solids (70%CW) at a temperature of 15-20°C (59-68°F), a flow rate of 450 m³/hr, and a pressure of 22 bar, required an urgent upgrade. The pipeline needed to be rapidly installed on a steep slope with a 60-meter (197-foot) drop, to enhance the capacity of the concentrator plant and integrate cyclones into the system.

Pexgol Solution

The 14-inch PE-X pipes from Pexgol, with a total length of 180 meters in two segments of 90 meters each, were the chosen solution. Using Pexgol fittings like Electrofusion Couplers, Stub Ends, and Support Bridges, the installation was completed in approximately 7 days by a specialized team. The process involved a Pexgol vertical uncoiler and two cranes, ensuring a quick and efficient setup. The critical benefits of the Pexgol piping system, such as quick installation, high chemical and corrosion resistance, lightweight handling, and long lengths, were key to making it ideal for the project.

Related Case Studies

Transport Of Palm Oil Slurry At 95°C.

Transport of Palm Oil Slurry

Loma Fresca
Colombia

 | 

2017
Installation Oof Pexgol Pipes through a Chimney for Compressed Air.

Transport of Compressed Air for Underground Mine

HMC Gold
Chile

 | 

2021
Installation of 1000 Meters of PE-X Pipe for an Underground Mine.

Mining Drainage Lines

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019
Potable Water Supply on Harsh Terrain

Potable Water Supply on Harsh Terrain

Mekorot / Beit Shemesh Water Company
Israel

 | 

2017
Groundwater Transportation With Ph Low Levels

Groundwater Transportation

Grupo México, Buena Vista del Cobre Mine
Mexico

 | 

2015
Installation of Pexgol Pipes for a Compress Air System.

Compressed Air System

Rav-Gon Printing House
Israel

 | 

2020