Skip to content

Pexgol Overcomes Extreme Dewatering Conditions in La Ciénega

A high-precision maneuver enabled the complete assembly of the system in record time, ensuring safety and operational continuity.

Case Study Nº

185

Customer

Fresnillo Plc.
Mexico

|

2025

Working Conditions

Temperature: 20°C (68°F) | Flow rate: 45 m³/h | Pressure: 440 psi | Fluid components: mine water with traces of chlorides, sulfates, calcium, magnesium, and iron

Pexgol Pipes

Pexgol 6″ SDR 6, Pexgol 6″ SDR 15

Application

Dewatering

Lenght

2000 m / 6561 ft

Categories

Pexgol Overcomes Extreme Dewatering Conditions in La Ciénega

The Challenge

At Fresnillo plc’s La Ciénega mining unit, located in Mexico, it was necessary to implement an underground dewatering system to transport water between two shafts spaced 150 meters horizontally and 240 meters vertically, using a single pump.

The project conditions were extremely demanding: the fluid—mine water with traces of chlorides, sulfates, calcium, magnesium, and iron—posed a high risk of corrosion and wear for conventional materials. Additionally, the installation had to be carried out through the ventilation tunnel (Robbins), which could only be temporarily stopped, leaving very limited time to complete the task.

Conventional solutions, such as steel or HDPE pipes, presented significant challenges in this type of application: difficult handling, numerous joints and long assembly times, added to the vulnerability of steel to corrosion under high pressure (440 psi) and the presence of abrasive minerals.

The Solution

Given these conditions, the Pexgol system was selected as the ideal alternative due to its resistance to abrasion, flexibility, and ease of installation. The installation included 500 meters of 6” SDR 6 (Class 30) Pexgol pipe and 1,500 meters of 6” SDR 15 (Class 11) pipe, supplied in long coils to reduce joints and ensure maximum safety and durability.

The pipe coil was transported to the mine entrance using a utility truck, and the maneuver required securing the line to the Robbins ventilation tunnel in a controlled reverse-feed process, guaranteeing correct alignment and minimizing potential failure points.

Due to the site’s operational restrictions—such as limited overhead space and the need to keep ventilation running—the full 500-meter installation was completed in record time, without incidents and in full compliance with mining safety standards.

Thanks to Pexgol’s on-site technical support, the contractor successfully executed the installation of this high-complexity system and completed the assembly within schedule. The result was a fast, safe, and highly reliable operation, demonstrating once again the robustness and performance of Pexgol systems in underground mining environments.

Related Case Studies

Pexgol Pipe Installation for Open Pit Mine Drainage.

Efficient Open Pit Mine Drainage

BHP Escondida Mine
Chile

 | 

2022
Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Hot & Abrasive Potash Brine Processing

Fertilizer Company
Canada

 | 

2017
Optimization of Water Systems in the Energy Industry.

“Threading” Pexgol Pipes

Pluspetrol
Argentina

 | 

2023
Pexgol: Delivering Rapid, Reliable & Long-lasting Mining Drainage Solutions

Addressing Drainage Challenges with Pexgol

Avino Mine
Mexico

 | 

2023
Installation of Pexgol Pipes to Transport Fish.

Fish Discharge Lines

TASA
Peru

 | 

2018

Categories:

Transport of acid slurry at high temperatures

Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2012