Water Transport on Crossroads

Transportation of water in more than 150 mining crossroads

Case Study Nº

26

Customer

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

|

2012

Working Conditions

Extreme environmental temperatures (-25°C to 40°C), 10 bars.

Pexgol Pipes

Pexgol 160 mm, Class 15 (SDR 11).

Application

Water transport.

Lenght

4000 m.

Categories

Transportation of water in more than 150 mining crossroads

The Challenge

Collahuasi Mine required to transport water that needed to cross mining crossroads, where the pipes where continuously exposed by the heavy trucks that circulate the area.

In the past, the client used HDPE pipes that created a bottleneck on the crossroads. To gain time they reinforced them with steel pipes that acted as steel protectors for the pipes. But still, the solution was very expensive.

Pexgol Solution

Since 2012 the client decided to replace all the water HDPE pipes with Pexgol. This change brought several benefits to the company, such us better productivity during the installation of the lines, better performance under harsh conditions, and thanks to its mechanical properties it improved the issues reducing the bottleneck on the crossroads.

The average installation time was reduced from 3-4 days to 4 hours per crossroad. On each one a Pexgol pipe was installed without a sand bed neither a steel protector. It only required a trench and a simple process to compact ground, using the natural field.

Related Case Studies

Transport of high corrosive material from the thickeners to the neutralization plant

Corrosive Material Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2015
Delivering Durability and Flexibility for a Sustainable Approach to Space Access.

Pioneering Space Launches with Ground-breaking Piping Solutions

SpinLaunch
USA

 | 

2021
Reduced wear and increased durability in the sand cleaning process at KSB de México.

Improving efficiency in steel foundry with Pexgol

KSB de Mexico
Mexico

 | 

2023
Hot Caustic Line Replacement in Paper Mill

Pulp & Paper Mill

Svetlogorskiy Mill
Russia

 | 

2015
Installation of a drainage system between a well and a mining dam.

Drinking Water on Sloping Terrain

AquaMag
Colombia

 | 

2019

Categories:

Successful outcome in pilot test for SCT Discharge Line with Pexgol.

Advanced piping solutions for handlingscaling fluids

Barrick Gold
Dominican Republic

 | 

2023