Water Transport on Crossroads

Transportation of water in more than 150 mining crossroads

Case Study Nº

26

Customer

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

|

2012

Working Conditions

Extreme environmental temperatures (-25°C to 40°C), 10 bars.

Pexgol Pipes

Pexgol 160 mm, Class 15 (SDR 11).

Application

Water transport.

Lenght

4000 m.

Categories

Transportation of water in more than 150 mining crossroads

The Challenge

Collahuasi Mine required to transport water that needed to cross mining crossroads, where the pipes where continuously exposed by the heavy trucks that circulate the area.

In the past, the client used HDPE pipes that created a bottleneck on the crossroads. To gain time they reinforced them with steel pipes that acted as steel protectors for the pipes. But still, the solution was very expensive.

Pexgol Solution

Since 2012 the client decided to replace all the water HDPE pipes with Pexgol. This change brought several benefits to the company, such us better productivity during the installation of the lines, better performance under harsh conditions, and thanks to its mechanical properties it improved the issues reducing the bottleneck on the crossroads.

The average installation time was reduced from 3-4 days to 4 hours per crossroad. On each one a Pexgol pipe was installed without a sand bed neither a steel protector. It only required a trench and a simple process to compact ground, using the natural field.

Related Case Studies

Pexgol’s piping system enabled Nexa Resources to revamp their waste management process, significantly reducing environmental impact.

Enhancing Nexa Resource’s Waste Management Using Pexgol Pipes

Nexa Resources
Brazil

 | 

2023
Overcoming Corrosion Challenges in the Oil Industry

Overcoming Corrosion Challenges in the Oil Industry

Petróleos Sudamericanos
Argentina

 | 

2023
Test Of Pexgol Pipes Vs Hdpe Pipes For Brine Transportation

Test: Pexgol vs HDPE for Brine Transportation

YBL
Bolivia

 | 

2017
Replacing steel pipes suffering from sediment formation

Transportation of Ore Slurry

RUSAL, aluminum factory
Russia

 | 

2012
High Pressure Water Transport for a Gold Mine.

High Pressure Water Transport

Mansfield Mine
Argentina

 | 

2019
600 Meters Installed in a Day: Pexgol Delivers for Kiewit in Power Project.

Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

Kimex
Mexico

 | 

2025