Skip to content

Water Transport on Crossroads

Transportation of water in more than 150 mining crossroads

Case Study Nº

26

Customer

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

|

2012

Working Conditions

Extreme environmental temperatures (-25°C to 40°C), 10 bars.

Pexgol Pipes

Pexgol 160 mm, Class 15 (SDR 11).

Application

Water transport.

Lenght

4000 m.

Categories

Transportation of water in more than 150 mining crossroads

The Challenge

Collahuasi Mine required to transport water that needed to cross mining crossroads, where the pipes where continuously exposed by the heavy trucks that circulate the area.

In the past, the client used HDPE pipes that created a bottleneck on the crossroads. To gain time they reinforced them with steel pipes that acted as steel protectors for the pipes. But still, the solution was very expensive.

Pexgol Solution

Since 2012 the client decided to replace all the water HDPE pipes with Pexgol. This change brought several benefits to the company, such us better productivity during the installation of the lines, better performance under harsh conditions, and thanks to its mechanical properties it improved the issues reducing the bottleneck on the crossroads.

The average installation time was reduced from 3-4 days to 4 hours per crossroad. On each one a Pexgol pipe was installed without a sand bed neither a steel protector. It only required a trench and a simple process to compact ground, using the natural field.

Related Case Studies

Bridging the Gap between Durability and Functionality in Harsh Processing Environments.

Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport

Syncrude
Canada

 | 

2022
Transport of Formation Water with Hydrocarbons.

Formation Water Transport

ROCH
Argentina

 | 

2015
Hot Caustic Line Replacement in Paper Mill

Pulp & Paper Mill

Svetlogorskiy Mill
Russia

 | 

2015
Boosting Productivity and Reducing Maintenance in Livestock Feed Production.

From Steel Struggles to Pexgol Progress

Ambar
Israel

 | 

2022
Pexgol technology can overcome challenges in shallow well applications, offering an efficient and cost-effective solution for leading companies in the agricultural industry.

Success in Agricultural Desalination: Water Supply Challenges

BerryMex
Mexico

 | 

2019
Replacing steel pipes suffering from sediment formation

Transportation of Ore Slurry

RUSAL, aluminum factory
Russia

 | 

2012