Case Study Nº

105

Customer

Rosebel Gold Mines – IamGold
Suriname

|

2020

Working Conditions

Pressure: 60 PSI | Flow: 70 m3/h | Temperature: 45°C | Fluid: Processed water

Pexgol Pipes

Pexgol 225 mm (8”)

Application

Processed water transportation

Lenght

100 m / 328 ft + elbows + tees + reducers

Categories

The Challenge

At the Rosebel Gold mine they had serious scale problems in the water transport line for the SAG Fees Chute mill.

They generally used steel pipes that ended up becoming encrusted, which resulted in them needing to be cleaned and on many occasions changed in periods of 3 to 5 months. This generated losses in production and a large cost for the maintenance that the steel required. Additionally, in the periods of use, the pumping pressures had to increase since the internal diameter of the pipe was reduced.

Pexgol Solution

The client was aware of the advantages of Pexgol to prevent fouling in lime slurry transport applications and therefore it was decided to proceed with a first section for testing.

With the Pexgol piping system, which has a low internal roughness, long radius elbows and mechanical accessories were supplied that helped ensure that even between the joints there were no interferences.

Today the system has been working for more than 10 months without problems or fouling, which is already a success for the client since its installation is simple and the costs are lower than steel pipes.

The connections were mechanical, it was only necessary to cut the pipe to size and place screws. PE-X is much lighter than steel, so fitting it to the pipe racks was also simple.

Additionally, the plant has Victaulic-type connections on the steel pipes, which made the job simple as Pexgol can also connect with Victaulic.

Related Case Studies

Транспортировка воды из скважины с низким pH.

Транспортировка воды на текстильной фабрике

CMT La Laguna
Мексика

 | 

2018
Линия питьевой воды высокого давления

Линия питьевой воды высокого давления

Компания Antofagasta Minerals, шахта Pelambres
Чили

 | 

2014
Addressing Scaling and Line Plugging with Advanced PE-X Piping.

Slurry: Pexgol’s Superior Alternative to Traditional Piping

Chip Manufacturer
USA

 | 

2022
В аэропорту Гайаны был установлен наружный гидрант и спринклеры внутри помещений

Линия водоснабжения и пожарной воды

Международный аэропорт Cheddi Jagan
Гайана

 | 

2018
Монтаж труб Pexgol для системы сжатого воздуха.

Система сжатого воздуха

Типография Rav-Gon
Израиль

 | 

2020
Транспортировка спирта концентрацией до 86% для производства рома и бренди

Транспортировка спирта для производства рома и бренди

Cuba Ron
Куба

 | 