Skip to content

Comprehensive Redesign of the PumpingSystem with Pexgol at the Sossego Mine

Replacing HDPE pipes with Pexgol allowed Vale to simplify operations, eliminate auxiliary equipment, and achieve a permanent installation under extreme conditions.

Case Study Nº

183

Customer

Vale
Brazil

|

2024

Working Conditions

Temperature: 25–38 °C | Flow rate: 600 m³/h | Pressure: 18.5 bar | Fluid components: Water

Pexgol Pipes

Pexgol PE-Xa Ø355 mm Class 30

Application

Open-pit dewatering (pumping recovered water)

Lenght

1,750 m (7 lines)

Categories

Comprehensive Redesign of the PumpingSystem with Pexgol at the Sossego Mine

The Challenge

With the depletion of the tailings dam at the Sossego mine, located in Canaã dos Carajás (Brazil), Vale needed to implement a new, reliable, and cost-effective pumping system capable of transporting recovered water back to the processing plant.\

The main challenge lay in the extremely demanding geographical conditions of the open-pit mine, with significant elevation differences and very rocky terrain.

Vale initially considered using conventional HDPE PE100 PN25 pipes. However, due to the excessive number of welds required, the system presented high risk, especially given the flow and pressure fluctuations within the mine.

This equipment posed additional operational hazards and demanded constant dismantling and relocation of pipe sections and supports by the personnel.

The total scope included more than 5,600 meters of piping, 466 unions, and a highly complex infrastructure with numerous electrofusion fittings and electrical controls. Vale required a more reliable, simple, resistant, and faster alternative—one capable of ensuring long-term operational continuity and minimizing shutdown times.

The Solution

Choosing Pexgol Ø355 mm Class 30 was a key decision for the project. Thanks to its unique mechanical properties—high flexibility, abrasion resistance, creep resistance, and durability under aggressive conditions—the pipe could fully withstand the demands of the new pumping system.

The redesign reduced the critical 250-meter section to 1,750 m of Pexgol pipe installed in seven independent lines, placed directly on rocky soil without the need for additional supports.

The new system includes:

  • 7 pumps of 542 HP each, operating with float switches.
  • 1,750 meters of Ø355 mm Pexgol pipe on 100 m and 50 m coils.
  • A fully automated system with frequency inverters and transformers for continuous operation.
  • ANSI Series 300 flanges, electrofusion saddles, and stiffening rings at each pump.
  • Local installation support from distributor local Rolcon, and weekly coordination with Vale, excavation, and operational teams.

Flexibility of Pexgol pipe minimized on-site unions thanks to long coil lengths, reducing welds and installation times, as well as significantly lowering potential failure points.

Results

 

DescriptionBefore (HDPE)After (Pexgol)
Total length5.600 m1.750 m
Welds46628
Floaters1757
Electrical centers21
Distribution network19 km12 km
Total platform weight130 tons61,5 tons
Booster system7 × 250 HPEliminated

Related Case Studies

Замена трубы ПЭНД на трубу компании Pexgol

Транспортировка суспензии

Шахта Tizapa
Мексика

 | 

2015
Explore how Pexgol pipe replacement addressed the corrosion issue in Gordon Pool’s saltwater delivery system, ensuring efficient operation.

From Steel to Pexgol: A Plumbing Upgrade for Tel Aviv’s Gordon Pool

Gordon Pool
Israel

 | 

2023
Монтаж труб Pexgol для транспортировки хвостов, образующихся при горной добыче.

Транспортировка хвостов с 50% содержанием твердых частиц

Golden Resource Corp. — Золотой рудник Дон Дэвид
Мексика

 | 

2019
Pan American Energy implements an efficient and sustainable solution for brine transportation.

Fast and Safe Brine Transport in the Salar de Hombre Muerto

Lithos (PAE)
Argentina

 | 

2024
Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Линия кислотного щелока c высокими уровнями абразивности и осаждения

Транспортировка абразивной жидкости

Компания Moa Nickel S.A. Sherritt
Куба

 | 

2014