Skip to content

Pexgol Piping for Fire Network System Expansion

How Pexgol piping improved the fire network system infrastructure in a paint manufacturing plant.

Case Study Nº

127

Customer

Wall
Argentina

|

2023

Working Conditions

Temperature: 25° to 30°C / 77° to 86°F | Pressure: 12 Kg/cm2

Pexgol Pipes

Pexgol 110 mm (3″), Class 15

Application

Fire network

Lenght

100 m / 328 ft

Categories

Pexgol Piping for Fire Network System Expansion

The Challenge

Pinturas Wall, a major industrial plant located in Borbollón, Las Heras district, Mendoza (Argentina), produces lines of household and industrial paints, coatings, and industrial paints, with an installed manufacturing capacity of 4,500,000 kiloliters per year. As part of the expansion of their factory, there was a need to expand their fire network system to ensure the safety of their operations.

The project required the installation of a new pipeline that could withstand a pressure of 12 kg/cm² and transport well water at temperatures between 25°C and 30°C. Additionally, the installation process needed to be efficient, minimizing the use of specialized machinery and labor.

Pexgol Solution

For this challenge, Pinturas Wall chose the 110 mm Class 15 Pexgol piping.
They installed 100 meters of this piping, using a range of accessories such as electrofusion couplers, mechanical double connectors, flanged couplers, stub ends, and loose flanges.

The choice of Pexgol was due to several advantages that this product offered. Firstly, its quick installation, as the laying and cutting of the piping was completed in a single day of work, while the execution of electrofusions and mechanical connections took only three days. Additionally, the piping is lightweight and easy to handle, allowing
it to be unrolled and backfilled with ease, minimizing the hours of machinery use.

Furthermore, Pexgol piping offered long lengths and remarkable material flexibility, further facilitating the installation process. Particularly notable was the ease of using the mechanical connectors, which were simple to install and did not require trained personnel, resulting in significant time and cost savings for Pinturas Wall.

This case study is a clear example of how Pexgol can provide efficient and costeffective solutions for complex challenges in the paint industry and beyond.

Related Case Studies

Фитинги Pexgol для транспортировки рассола в бразильской химической компании.

Высокая коррозионная стойкость к рассолу

Unipar Carbocloro
Бразилия

 | 

2019
Bridging the Gap between Durability and Functionality in Harsh Processing Environments.

Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport

Syncrude
Canada

 | 

2022
Монтаж линии Pexgol на глубине 200 метров в подземном руднике

Транспортировка сжатого воздуха

Рудник Meridian — Faena El Peñón
Чили

 | 

2018
Транспортировка грязной воды (жидкие отходы производства пальмового масла) с высоким содержанием органических веществ.

Транспортировка грязной воды на заводе по переработке пальмового масла

La Gloria
Колумбия

 | 

2020
Транспортировка пластовой воды с углеводородами.

Транспортировка пластовой воды

ROCH
Аргентина

 | 

2015
Установка труб на горе

Транспортировка талых стоков

Компания Codelco Andina, проект TADA 1-2
Чили

 | 

2013