Skip to content

Transportation of Water with Solids

Pexgol Pipe Installation for the Transport of Water with Solids (Feathers, Bones, Viscera, Etc.)

Case Study Nº

111

Customer

Kofanor
Mexico

|

2022

Working Conditions

Fluid: process water with solids (feathers, bones, viscera, etc.) | Temperature: 26°C / 78°F | Gravity transport

Pexgol Pipes

Pexgol 6”, class 11

Application

Transport of process water with solids

Lenght

160 m / 524 ft

Categories

The Challenge

Kofanor, a Mexican industrial company dedicated to the transformation of meat waste into flour and oil through a thermal process, resulting in a protein ingredient for the manufacture of animal feed.

Kofanor was looking to install an underground line to transport process water from a manhole to a sump. Two options were contemplated for this project, carbon steel or stainless steel pipes, however the first one was not an option due to the corrosion that they present over time, and stainless steel resulted in a very high operating cost.

Pexgol Solution

It was decided to use Pexgol due to the great facility to carry out the installation, where no joint or sand bed was required for the 140 meters of route where the pipe would be buried. Pexgol was cheaper compared to carbon steel and stainless steel.

Likewise, no special equipment was required to carry out the installation, since the plant had a backhoe and forklift with which they were able to uncoil the pipe without any problem.

Related Case Studies

Pexgol extends pipe lifespan and reduces maintenance in salt production.

Fewer Shutdowns, Greater Efficiency: Pexgol in the Salt Industry

Sales del Istmo
Mexico

 | 

2023
The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
Installation of Pexgol Pipes for Drainage of an Underground Mine

Vertical Drain in Underground Mine

Meridian Mine - Faena El Peñón
Chile

 | 

2018
Enhancing Efficiency and Durability in the Construction of Aerial Pipelines.

Facing the Challenges of the Neuquén Terrain in Argentina

Pluspetrol
Argentina

 | 

2023
How Pexgol piping improved the fire network system infrastructure in a paint manufacturing plant.

Pexgol Piping for Fire Network System Expansion

Wall
Argentina

 | 

2023
Прокладка труб из сшитого ПЭ длиной 3000 метров для подземного рудника.

Дренажные линии в подземном руднике

Lundin Mining — Рудник Канделария-Норте
Чили

 | 

2020