Transporting Brine at High Pressure

Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Case Study Nº

100

Customer

Mekorot
Israel

|

2020

Working Conditions

Pressure: 36 bar | Flow rate: 120 m^3/hr | Chloride concentration: 10,100 mg/l

Pexgol Pipes

Pexgol 250 mm (10”) Class 43

Application

Brine transport at a Borehole

Lenght

300 m / 984 ft

Categories

The Challenge

Mekorot, the national water company of Israel and the country’s top agency for water management, required a corrosion resistant pipe that could hold very high pressure in a deep borehole (300 m). Furthermore, the pipe needed to be able to resist Chloride concentration of 10,100 mg/l.a

Pexgol Solution

A custom-made Pexgol pipe was installed (pipe 250 mm, class 43). The Pexgol pipe was provided in two coils of 150 m each. The two coils were connected by a special coupler that can hold the weight and the high pressure.

The other option that Mekorot considered was a pipe made of super duplex. Since installation of super duplex would take around 3 weeks and cost (approximately) 3,000,000 NIS ($9.3K) while installation of a Pexgol pipe is 3 days and cost about half. Pexgol pipe was the obvious choice.

Related Case Studies

Overcoming Corrosion Challenges in the Oil Industry

Overcoming Corrosion Challenges in the Oil Industry

Petróleos Sudamericanos
Argentina

 | 

2023
Испытательная установка для транспортировки кварцевого песка.

Транспортировка кварцевого песка: сравнение ПЭВП и Pexgol

Covia Corp
Мексика

 | 

2019
Delivering Durability and Flexibility for a Sustainable Approach to Space Access.

Pioneering Space Launches with Ground-breaking Piping Solutions

SpinLaunch
USA

 | 

2021
Установка труб на горе

Транспортировка талых стоков

Компания Codelco Andina, проект TADA 1-2
Чили

 | 

2013
Прокладка труб из сшитого ПЭ длиной 3000 метров для подземного рудника.

Дренажные линии в подземном руднике

Lundin Mining — Рудник Канделария-Норте
Чили

 | 

2020
850 Meters of Pipe Replaced in Less Than 24 Hours, Without Affecting Residents.

Goodbye Asbestos: Pexgol Modernizes Thermal Water Network

Raquet Club Lake Chapala
Mexico

 | 

2024