Skip to content

Water Transport for Fire Network

Replacement of Carbon Steel Pipes by Pexgol for Fire Fighting Network.

Case Study Nº

117

Customer

Profertil
Argentina

|

2022

Working Conditions

Pressure: 15 bars | Temperature: Ambient

Pexgol Pipes

Pexgol 180 (6″), 225 (8″) & 280 (12″) mm, Class 15

Application

Water transport for fire network

Lenght

1000 m / 3280 ft

Categories

The Challenge

Profertil, an Argentine company specializing in the manufacture of fertilizers, has a fire network that is more than 10 years old working with carbon steel pipes.

Given that the water they transport has a high chloride content, the lines were affected by corrosion and in many cases even with scale that obstructed the pipe by 50%.

Pexgol Solution

In order to have an efficient fire-fighting network, the Profertil project team opted for a plastic pipe that does not suffer from corrosion, with less possibility of incrustations and its installation does not require specialized machinery.

Likewise, given bad experiences with other types of pipes in relation to installation and operation, the maintenance team carried out pressure tests and resistance to external damage with a sample that was delivered to them.

Finally, 3 lines with Pexgol pipes were installed and it is scheduled in other stages to completely replace the fire network, a total estimate of 7 km.

Electrofusion joints and accessories were used to carry out the derivations and changes of direction.
In relation to other materials and considering that in several places where the pipe had to be buried, obstacles were found from cables and other pipes, the installation was successful.

Related Case Studies

Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Линии подачи пресс-фильтра LASTA2

Транспортировка концентрированной медной руды

Компания BHP Billiton, месторождение, Olympic Dam, Австралия
Австралия

 | 

2014
Pexgol Pipe Installation for Open Pit Mine Drainage.

Efficient Open Pit Mine Drainage

BHP Escondida Mine
Chile

 | 

2022
Replacing HDPE pipes with Pexgol allowed Vale to simplify operations, eliminate auxiliary equipment, and achieve a permanent installation under extreme conditions.

Comprehensive Redesign of the PumpingSystem with Pexgol at the Sossego Mine

Vale
Brazil

 | 

2024
Монтаж труб Pexgol на рыбзаводе.

Транспортировка рыбьего жира при 36 °C / 96,8 °F

Компания Guaymas Protein
Мексика

 | 

2018
Bridging the Gap between Durability and Functionality in Harsh Processing Environments.

Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport

Syncrude
Canada

 | 

2022