Fast and Safe Brine Transport in the Salar de Hombre Muerto

Pan American Energy implements an efficient and sustainable solution for brine transportation.

Case Study Nº

171

Customer

Lithos (PAE)
Argentina

|

2024

Working Conditions

Temperature: 20°C / 58°F | Flow rate: 80.3 m³/h | Pressure: 8.6 bar | Fluid: Brine

Pexgol Pipes

Pexgol 160 mm (6″) class 10

Application

Brine transport

Lenght

10,000 m / 32808.4 ft

Categories

Fast and Safe Brine Transport in the Salar de Hombre Muerto

The Challenge

Pan American Energy, a leader in oil, gas, and renewable energy exploration and production, faced a logistical challenge during the performance testing phase of its lithium mining project (Lithos) in the Salar de Hombre Muerto, Argentina. The company needed a reliable and flexible transport line for brine transfer between pumping wells, in a demanding salt flat environment.

The project called for a solution capable of withstanding abrasive terrain, enduring constant movement between wells, and ensuring pipeline integrity throughout the process. At the same time, Pan American Energy aimed to reduce operational costs and minimize environmental impact, in line with its sustainability objectives.

The Solution

To meet these challenges, Pan American Energy installed 10 kilometers of 6-inch Pexgol pipes in 450-meter coils. This solution proved ideal due to the following advantages:

  • Quick Installation: Each 450-meter coil was deployed in just 15 minutes, significantly reducing installation time and enabling quick movement between wells.
  • High Chemical and Abrasion Resistance: Pexgol pipes withstood the abrasive terrain and extreme weather conditions of the Salar de Hombre Muerto, ensuring uninterrupted operation without damage.
  • Long Sections: The use of long-length coils minimized the number of joints required, reducing potential failure points and improving pipeline safety.

The operation was highly efficient: each well was tested for a set duration, and afterward, the same pipe was dragged to the next well, eliminating the need for multiple lines. This method allowed Pan American Energy to optimize resources, lower costs, and speed up its testing schedule.

Related Case Studies

Mining Effluent Transportation in Cuba.

Pexgol Optimizes Tailings Management at Sherritt’s Moa Nickel Mine

Sherritt
Cuba

 | 

2020
Minas Argentinas Replaces HDPE with Pexgol in Its Secondary Leaching Project

Efficient and Safe Irrigation in Secondary Leaching with Pexgol

Minas Argentinas S.A.
Argentina

 | 

2025
Replacement of a HDPE Pipe for a Pexgol Pipe

Slurry Transportation

Sabinas Mine
Mexico

 | 

2017
Pexgol’s resistance to scaling and chemicals delivers consistent operation in open-pit mining.

Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

Buena Vista del Cobre
Mexico

 | 

2024
Pexgol Transforms Tailings Transportation at Minera San Julián.

Minera San Julián Adopts Pexgol to Improve Water Management

Fresnillo plc
Mexico

 | 

2024
Installation of Pexgol Pipes to Transport Fish.

Fish Discharge Lines

TASA
Peru

 | 

2018

Categories: