Fast and Safe Brine Transport in the Salar de Hombre Muerto

Pan American Energy implements an efficient and sustainable solution for brine transportation.

Case Study Nº

171

Customer

Lithos (PAE)
Argentina

|

2024

Working Conditions

Temperature: 20°C / 58°F | Flow rate: 80.3 m³/h | Pressure: 8.6 bar | Fluid: Brine

Pexgol Pipes

Pexgol 160 mm (6″) class 10

Application

Brine transport

Lenght

10,000 m / 32808.4 ft

Categories

Fast and Safe Brine Transport in the Salar de Hombre Muerto

The Challenge

Pan American Energy, a leader in oil, gas, and renewable energy exploration and production, faced a logistical challenge during the performance testing phase of its lithium mining project (Lithos) in the Salar de Hombre Muerto, Argentina. The company needed a reliable and flexible transport line for brine transfer between pumping wells, in a demanding salt flat environment.

The project called for a solution capable of withstanding abrasive terrain, enduring constant movement between wells, and ensuring pipeline integrity throughout the process. At the same time, Pan American Energy aimed to reduce operational costs and minimize environmental impact, in line with its sustainability objectives.

The Solution

To meet these challenges, Pan American Energy installed 10 kilometers of 6-inch Pexgol pipes in 450-meter coils. This solution proved ideal due to the following advantages:

  • Quick Installation: Each 450-meter coil was deployed in just 15 minutes, significantly reducing installation time and enabling quick movement between wells.
  • High Chemical and Abrasion Resistance: Pexgol pipes withstood the abrasive terrain and extreme weather conditions of the Salar de Hombre Muerto, ensuring uninterrupted operation without damage.
  • Long Sections: The use of long-length coils minimized the number of joints required, reducing potential failure points and improving pipeline safety.

The operation was highly efficient: each well was tested for a set duration, and afterward, the same pipe was dragged to the next well, eliminating the need for multiple lines. This method allowed Pan American Energy to optimize resources, lower costs, and speed up its testing schedule.

Related Case Studies

Замена трубы из углеродистой стали на трубу компании Pexgol

Транспортировка воды

Компания Cargill
Мексика

 | 

2017
Installation of a Pexgol Line for the Transport of Formation Water in an Oil Company.

Replacement of Metal Pipe with PE-X for Formation Water

Enap Sipetrol Ecuador
Ecuador

 | 

2022
Отвод воды из шахты

Отвод воды из шахты

Компания El Peñón Yamana Gold, шахта Meridian
Чили

 | 

2016
Adapting to the demands of the process: how Pexgol solves the problems of corrosion and abrasion in the extraction of palm oil.

Implementation of Pexgol Pipelines for the Transport of Muddy Water

IACSA
Colombia

 | 

2023
Прокладка труб из сшитого ПЭ длиной 1000 метров для подземного рудника.

Рудничные дренажные линии

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019
Reducing maintenance and increasing safety in hydraulic backfill operations.

Pexgol Simplifies Slurry Transportation at Buriticá Mine

Zijin - Continental Gold
Colombia

 | 

2023