Water Lines – High Pressure Water Feed Lines

Water line feed from wells to mine

Case Study Nº

5

Customer

Yamana Gold, Meridian Mine
Chile

|

2012

Working Conditions

High pressure (over 24 bar), corrosion and ambient temperature at 40°C/104°F. The first 2,750 meters of pipes were covered in sand, the last 2,750 meters were exposed to the sun.

Pexgol Pipes

Pexgol 225×30.8, Class 24.

Application

Dewatering.

Lenght

5,500 meters.

Categories

Water Lines – High Pressure Water Feed Lines

The Challenge

The high pressure and corrosion caused constant failure of the two initial parallel steel pipelines and serious threats to the production process.

One steel pipeline was out of service for at least two years and the other suffered from severe corrosion. Since this was the only main line transporting water to the production line, it was critical for the whole production process. The client required a highly durable and a quick install solution for non-stop performance

Pexgol Solution

The replacement of the steel pipeline with Pexgol’s flexible and high resistance to corrosion pipe solution eliminated previous failures. In addition, Pexgol supplied easy-to-install longer pipes.

The client is so pleased with the solution that he will be replacing the HDPE pipes that are part of this line as well.

Related Case Studies

Dewatering without Supports

Open Cast Mine Dewatering

El Volcan Mine Arcelor Mittal
Mexico

 | 

2017
Replacement of Carbon Steel Pipes by Pexgol for Fire Fighting Network.

Water Transport for Fire Network

Profertil
Argentina

 | 

2022
Slurry transportation with high nickel levels

Leached Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2013
Replacement of a HDPE Pipe for a Pexgol Pipe

Compressed Air Transportation

Saucito S.A. de C.V. Mine
Mexico

 | 

2017
Case Study: Pexgol’s Solution at the Palm Oil Plant.

Efficiency and Durability in Handling Muddy Water

Industrial Aceitera del Casanare
Colombia

 | 

2023
Replacing steel pipes suffering from sediment formation

Transportation of Ore Slurry

RUSAL, aluminum factory
Russia

 | 

2012