Water Drainage at an Underground Mine
Water Drainage From the Inside of an Underground Mine
Case Study Nº
31
Customer
El Peñón Yamana Gold, Meridian Mine
Chile
|
2016
Working Conditions
Extreme temperatures (-5° to 38°C).
Pexgol Pipes
Pexgol 160 mm Class 15 (SDR 11).
Application
Water drainage.
Lenght
600 m.
Categories

The Challenge
The water drainage from the inside of Meridian underground mine was processed through an HDPE 12 meter pipe that required 50 joints to be installed. The total installation time was 4 days, with no chance to minimize costs. Furthermore, the pump operated over it efficiency levels.
Pexgol Solution
A 600 meters Pexgol pipe 160 mm Class 15 was provided, in one section without joints. The Pexgol pipe was carried for 6 kilometers in 2 turns, which caused as a result 50% of time saved in the installation.
Due to the lower load losses, now the pump operates at its mayor efficiency level.
Related Case Studies
From Steel Struggles to Pexgol Progress
Ambar
Israel
|
2022
Dewatering Through Shafts
Esan Eczacibasi Endustriyel Hammaddeler
Turkey
|
2019
Overcoming Geotechnical Challenges with Pexgol at Media Luna
Minera Media Luna
Mexico
|
2023
Industrial Waste Water to MBR Treatment Facility
Chip Manufacturer
Israel
|
2021