Water Drainage at an Underground Mine

Water Drainage From the Inside of an Underground Mine

Case Study Nº

31

Customer

El Peñón Yamana Gold, Meridian Mine
Chile

|

2016

Working Conditions

Extreme temperatures (-5° to 38°C).

Pexgol Pipes

Pexgol 160 mm Class 15 (SDR 11).

Application

Water drainage.

Lenght

600 m.

Categories

Water Drainage From The Inside Of An Underground Mine

The Challenge

The water drainage from the inside of Meridian underground mine was processed through an HDPE 12 meter pipe that required 50 joints to be installed. The total installation time was 4 days, with no chance to minimize costs. Furthermore, the pump operated over it efficiency levels.

Pexgol Solution

A 600 meters Pexgol pipe 160 mm Class 15 was provided, in one section without joints. The Pexgol pipe was carried for 6 kilometers in 2 turns, which caused as a result 50% of time saved in the installation.

Due to the lower load losses, now the pump operates at its mayor efficiency level.

Related Case Studies

Potable Water Supply on Harsh Terrain

Potable Water Supply on Harsh Terrain

Mekorot / Beit Shemesh Water Company
Israel

 | 

2017
 How Pexgol streamlined water transportation at Zuccardi Winery

Fast and Reliable Solution for Winemaking Processes

Zuccardi Winery
Argentina

 | 

2024
Installation of Pexgol Pipe for Transportation of Mining Tailings.

Tailings Transport with 50% solids

Golden Resource Corp. – Don David Gold Mine
Mexico

 | 

2019
Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

Palm Oil: Transport of Leached Mud

Industria Chiquibul
Guatemala

 | 

2018
Transport of acid slurry at high temperatures

Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2012
Pexgol Pipe Installation for Open Pit Mine Drainage.

High Pressure Dewatering in Open Pit Mine

Lundin Mining
Chile

 | 

2021