2015

Working Conditions

Underground work (-250 m).

Pexgol Pipes

Pexgol 90 mm (SDR 7.4).

Application

Water transportation

Lenght

200 m.

Categories

Groundwater Transportation With Ph Low Levels

The Challenge

At “Buena Vista del Cobre” Mine the process water was extracted from deep wells. Formerly they worked with stainless steel pipes 316 with 9 months of operational lifetime that required to be replaced due to the corrosion, as a consequence of the low pH (between 1.5 and 2.5) from the groundwater.

Pexgol Solution

The client required a more flexible pipe, with longer operational lifetime than the steel, and minimize the stops at the plant. Therefore, a 3 inch Pexgol pipe was installed in one section, holding the weight of the pump, the cables, the water column and the pipe itself. The new pipe operational lifetime is 50 years.

The client received not only a durable pipe but also a complete solution including fittings for the pump and the discharge head. For a 3 inch 250 meter steel pipe, it would require more than 40 thread joints.

With Pexgol it only took 2 joints. This operation with a steel pipe it would cost $22.000 USD, when a Pexgol operation cost just a third of it. Plus the savings the client got from avoiding to stop the production for the failures.

Related Case Studies

The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Improvement in Brine Management through Pexgol Piping

Sales de Jujuy
Argentina

 | 

2023
Transportation of water with solids from an open cast mine

Open Cast Mine Dewatering

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2013
Acid liquor line with high levels of abrasion and sedimentation

Abrasive Liquid Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2014
Reduction of material build-up in brine and brine/acid lines

Mineral Processing – Brine Transportation

SQM,Pedro Valvidia Mine
Chile

 | 

2010
Pexgol Fittings for Brine Transportation at a Brazilian Chemical Company.

High Corrosion Resistance Against Brine

Unipar Carbocloro
Brazil

 | 

2019
Performance evaluation of Pexgol lining under extreme service conditions.

Durable Solution Against Abrasion in Production Facilities: Pexgol at YPF

YPF
Argentina

 | 

2018