Groundwater Transportation

Groundwater Transportation With Ph Low Levels

Case Study Nº

29

Customer

Grupo México, Buena Vista del Cobre Mine
Mexico

|

2015

Working Conditions

Underground work (-250 m).

Pexgol Pipes

Pexgol 90 mm (SDR 7.4).

Application

Water transportation

Lenght

200 m.

Categories

Groundwater Transportation With Ph Low Levels

The Challenge

At “Buena Vista del Cobre” Mine the process water was extracted from deep wells. Formerly they worked with stainless steel pipes 316 with 9 months of operational lifetime that required to be replaced due to the corrosion, as a consequence of the low pH (between 1.5 and 2.5) from the groundwater.

Pexgol Solution

The client required a more flexible pipe, with longer operational lifetime than the steel, and minimize the stops at the plant. Therefore, a 3 inch Pexgol pipe was installed in one section, holding the weight of the pump, the cables, the water column and the pipe itself. The new pipe operational lifetime is 50 years.

The client received not only a durable pipe but also a complete solution including fittings for the pump and the discharge head. For a 3 inch 250 meter steel pipe, it would require more than 40 thread joints.

With Pexgol it only took 2 joints. This operation with a steel pipe it would cost $22.000 USD, when a Pexgol operation cost just a third of it. Plus the savings the client got from avoiding to stop the production for the failures.

Related Case Studies

Installation of Pexgol Pipes for a Free Chlorine Potable Water Supply.

Free Chlorine Potable Water Supply

Rabin Medical Center
Israel

 | 

2020
Pexgol and Fresnillo: Allies in innovative piping solutions for mining.

Safety and durability: The heart of our solutions

Minera Fresnillo
Mexico

 | 

2021
Hot sylvinite leach at 114°C/237°F

Mineral Processing – Potash Processing Plant

ICL group, Dead Sea Works
Israel

 | 

1987
Installation of a Pexgol Pipe on top of a Steel Outdated Pipe

Carriage of Chemicals at Sea Port

Ashdod Sea Port
Israel

 | 

2016
Installation of 1000 Meters of PE-X Pipe for an Underground Mine.

Mining Drainage Lines

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019
Lasta2 Filter Press Feed Lines

Concentrated Copper Transportation

BHP Billiton, Olympic Dam, Australia
Australia

 | 

2014