Skip to content

Vertical Drain in Underground Mine

Installation of Pexgol Pipes for Drainage of an Underground Mine

Case Study Nº

67

Customer

Meridian Mine – Faena El Peñón
Chile

|

2018

Working Conditions

Underground work

Pexgol Pipes

Pexgol 160 mm (6”), Class 15 | Pexgol 160 mm (6”), Class 19 | Pexgol 200 mm (8”), Class 26.7

Application

Mine Dewatering

Lenght

800 m

Categories

Installation of Pexgol Pipes for Drainage of an Underground Mine

The Challenge

The Meridian mine (Faena El Peñón) required the installation of a line for the drainage of high-pressure water from the lower level of the mine, passing through the vertical ventilation chimney with a height of 150 meters, continuing through the interior of the mine until an outdoor pool.

Pexgol Solution

The client decided to install 800 m of Pexgol pipes in three di erent sizes:
Pexgol 160 mm (6”) Class 15, 160 mm (6”) Class 19 and 200 mm (8”) Class 26.7.
The installation was very simple:

  • Lifting was carried out in the ventilation chimney.
  • Mechanical connections were used that did not require special tools for installation.
  • In the upper area the pipes were placed on supports provided by the mining company.

Pexgol was selected due to its capabilities:

  • Possibility of supply in long lengths minimizing the connections to only 4.
  • Ability to withstand the drag of more than 5 km from outside to the final assembly point inside the underground mine.
  • Ability to withstand creep involved in vertical mounting of 150 meters.

Related Case Studies

Enhanced hydraulic and structural reliability for critical community infrastructure.

Optimization of Potable Water Supply for 1,600 residents

Rincón de la Candelaria
Mexico

 | 

2025
An Outdoor Hydrant and Indoor Sprinklers were installed at Guyana Airport

Water Supply & Fire Extinguisher Line

Cheddi Jagan International Airport
Guyana

 | 

2018
Replacement of Carbon Steel Pipe for a Pexgol Pipe

Water Transportation

Cargill
Mexico

 | 

2017
Cement Slurry Injection to an Underground Mine

Backfill

Aguilar Mine
Argentina

 | 

2015
Installation of Pexgol Pipesf for the Drainage of an Underground Mine.

High Pressure Drain in Underground Mine

Ojos del Salado Mine – Lundin Mining
Chile

 | 

2018
Pexgol’s resistance to scaling and chemicals delivers consistent operation in open-pit mining.

Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

Buena Vista del Cobre
Mexico

 | 

2024