Installation of 3000 Meters Of PE-X Pipe for an Underground Mine.

Case Study Nº

73

Customer

Lundin Mining – Candelaria Norte Mine
Chile

|

2020

Working Conditions

Underground work

Pexgol Pipes

Pexgol 160 mm (6”), class 19

Application

Dewatering

Lenght

3000 m

Categories

Installation of 3000 Meters Of PE-X Pipe for an Underground Mine.

The Challenge

Lundin Mining at Calendaria Norte Mine had to install a drainage line for its underground mine, where the main challenge was to pass it through the main ramp of the mine, which is only available once a month during its maintenance (since the operation of the mine cannot be stopped).

Pexgol Solution

The client decided to install 3,000 meters of Pexgol pipe that was supplied in five coils of 600 meters each. Two main maintenances were scheduled, where three coils per day (1800 meters) were unrolled and installed.

Cross-linked polyethylene was chosen because of:

  • Its long-length supply format.
  • Ease of installation, thanks to the flexibility of the pipe that was easy to accommodate in the curves of the interior of the mine.
  • Limited installation times to avoid stopping the mining operation.

Installation was quick and easy, uncoiling the full length of the pipeline and then dragging it into the mine.

Related Case Studies

600 Meters Installed in a Day: Pexgol Delivers for Kiewit in Power Project.

Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

Kimex
Mexico

 | 

2025
Installation of a Drainage System between Dams in a Copper Mine.

Water Transport Between Dams

CODELCO – El Teniente Mine
Chile

 | 

2019
Pexgol’s resistance to scaling and chemicals delivers consistent operation in open-pit mining.

Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

Buena Vista del Cobre
Mexico

 | 

2024
Transport of Concentrated Alcohol to 86% for the Production of Rum and Brandy

Transportation of Alcohol for the Production of Rum and Brandy

Cuba Ron
Cuba

 | 

2016
Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Transportation of mixed liquid and corrosive vapor (H2S) from the dehumidifiers

Mineral Processing Corrosive Liquid & Vapor

Moa Nickel S.A. Sherritt
Cuba

 | 

2011