Skip to content

Water Transport Between Dams

Installation of a Drainage System between Dams in a Copper Mine.

Case Study Nº

77

Customer

CODELCO – El Teniente Mine
Chile

|

2019

Working Conditions

Extreme temperatures -10° to 40°C / 14° to 104°F

Pexgol Pipes

Pexgol 160 mm (6”), class 15

Application

Dewatering

Lenght

5600 m / 18372.7 ft

Categories

Installation of a Drainage System between Dams in a Copper Mine.

The Challenge

Cooperación del Cobre de Chile (CODELCO) required transporting water from the Barahona dam to a specific sector of the Caletones smelter, located south of the dam. The line was due to be installed in less than 10 weeks.

The distance of the route, in addition to other works being carried out on site and the vehicular flow, made it critical that the pipeline needed to be installed in the shortest time possible.

Pexgol Solution

The client made an economic evaluation, considering the installation time of the HDPE versus PE-X pipes from Pexgol. Pexgol was finally chosen.

The delivery format in coil of long lengths, allowed the totality of meters to be delivered in only 10 coils.
Installation was exceptionally fast. The uncoiling allowed up to 6 drums per day to be released, the sections to be located in their final location and subsequently joined with the relevant couplings, within 6 days.

As for the accessories, 9 electrofusion couplings were used.
The final experience was very satisfying.

Related Case Studies

Coarse NACL (SALT) Dredging Tailing

Slurry Lines – Abrasive Dredged Material

ICL group, Dead Sea Works
Israel

 | 

1992
Reducing maintenance and increasing safety in hydraulic backfill operations.

Pexgol Simplifies Slurry Transportation at Buriticá Mine

Zijin - Continental Gold
Colombia

 | 

2023
EMESA Optimizes Formation Water Transportation in Mendoza.

Pexgol’s Solution in Secondary Recovery for EMESA

EMESA
Argentina

 | 

2023
Dewatering without Supports

Open Cast Mine Dewatering

El Volcan Mine Arcelor Mittal
Mexico

 | 

2017
Pexgol Fittings for Brine Transportation at a Brazilian Chemical Company.

High Corrosion Resistance Against Brine

Unipar Carbocloro
Brazil

 | 

2019
Pexgol’s Role in Enhancing Guaymas Protein’s Operations.

Transition to Corrosion-Free Diesel Delivery Systems

Guaymas Protein
Mexico

 | 

2023