Drainage System

Installation of a Drainage System in an Open Pit Mine.

Case Study Nº

76

Customer

BHP Pampa Norte – Cerro Colorado Mine
Chile

|

2020

Working Conditions

Extreme temperatures 10°C to 35°C / 50°F to 95°F

Pexgol Pipes

Pexgol 200 mm (8”), class 21

Application

Dewatering

Lenght

450 m

Categories

Installation of a Drainage System in an Open Pit Mine.

The Challenge

BHP at Cerro Colorado Mine required to implement a dewatering system from the bottom of the mine.
For this type of applications, a meticulous engineering study was carried out, considering the terrain plus constructive and operational aspects.

In detail, some of these aspects are: the complexities of the terrain, the dimensions and distances of the trace, high fluid conduction pressures, extreme environmental temperatures, demands on mechanical resistance due to pipeline drag, possible material collapses, minimize connections, minimize assembly times and mine availability for operation.

Pexgol Solution

After consulting with the local team (Crosspipe Systems), the client decided to install 450 meters of Pexgol 200 mm class 21 pipe.
Crosspipe provided contributions in the calculation and design of the trace, using the engineering background provided by the client, as well as on-site consultancies.

In addition to the above, the advantageous characteristics presented by Pexgol pipes in this application were:

  • Delivery of sections in long lengths.
  • Coil supply format, simple uncoiling activity.
  • Mechanical resistance to subcritical crack growth. Resists drag in mining terrain and landslides.
  • Minimize connections (only 2 connections were made).
  • Able to resist high internal fluid pressures. Maximum internal pressure to date is 52 bar.
  • Resistance to extreme temperatures -50°C to 110°C.
  • Internal roughness of 0.0006mm (60% less than conventional HDPE) contributes to energy savings due to lower pressure drops.
  • Radius of curvature 5 times less than conventional HDPE, avoids the use of elbow connectors and accessories.
  • Manufacturing and local technical support, with immediate response times.

Also, the installation was quick and without special equipment or tools.

Related Case Studies

Replacement of a HDPE Pipe for a Pexgol Pipe

Compressed Air Transportation

Saucito S.A. de C.V. Mine
Mexico

 | 

2017
In an engineering challenge, the Pexgol 225 mm (8”) Class 15 pipe proved to be the perfect solution for transporting tailings at the Mina Capela mining complex.

Environmental Protection and Efficiency in Tailings Management

Mina Capella - Grupo Peñoles
Mexico

 | 

2023
Extraction of underground water through wells

Extraction of Underground Water

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2010
Pexgol: Delivering Rapid, Reliable & Long-lasting Mining Drainage Solutions

Addressing Drainage Challenges with Pexgol

Avino Mine
Mexico

 | 

2023
Pexgol’s resistance to scaling and chemicals delivers consistent operation in open-pit mining.

Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

Buena Vista del Cobre
Mexico

 | 

2024
Transportation of water with solids from an open cast mine

Open Cast Mine Dewatering

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2013