Open Cast Mine Dewatering

Transportation of water with solids from an open cast mine

Case Study Nº

25

Customer

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

|

2013

Working Conditions

Extreme environmental temperatures (-25°C to 40°C).

Pexgol Pipes

Pexgol 225 mm, Class 24 (SDR 7.4).

Application

Mine dewatering.

Lenght

4000 m.

Categories

Transportation of water with solids from an open cast mine

The Challenge

Collahuasi Mine required to transport water from the cast mine. Due to the harsh environmental conditions of the field, the engineering team decided to make a change on the type of material they have been using historically.

Pexgol Solution

A 4,000 meter Pexgol pipe was installed from the bottom of the cast mine to the load area. It required a Pexgol pipe 225 mm Class 24, in long sections of 320 meters that enabled an easy installation.

The Pexgol pipe was design to resist the working life cycle of the dewatering system, without suffering any damages on the pipe itself, the operations or the employees working on it.

Collahuasi Mine has become one of the Golan’s key clients regarding the use of dewatering lines among Chile’s mines. The pipe installed has been in use since 2013 with no failures.

Related Case Studies

Transportation of water in more than 150 mining crossroads

Water Transport on Crossroads

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2012
A high-precision maneuver enabled the complete assembly of the system in record time, ensuring safety and operational continuity.

Pexgol Overcomes Extreme Dewatering Conditions in La Ciénega

Fresnillo Plc.
Mexico

 | 

2025
Performance evaluation of Pexgol lining under extreme service conditions.

Durable Solution Against Abrasion in Production Facilities: Pexgol at YPF

YPF
Argentina

 | 

2018
Installation of Pexgol pipes for the transport of formation water (gas and minerals)

Gas Wells: Formation Water Treatment

Canacol
Colombia

 | 

2018
Test Of Pexgol Pipes Vs Hdpe Pipes For Brine Transportation

Test: Pexgol vs HDPE for Brine Transportation

YBL
Bolivia

 | 

2017
Water Transportation through Shafts

Open Cast Mine Dewatering

Agnico Eagle Pinos Altos Mine
Mexico

 | 

2017