High Pressure Water Transport

High Pressure Water Transport for a Gold Mine.

Case Study Nº

86

Customer

Mansfield Mine
Argentina

|

2019

Working Conditions

Exposed pipe with repump systems at 21 bar (305 PSI)

Pexgol Pipes

Pexgol 225 mm (8″), class 24, 19, 15 & 12

Application

Water transport

Lenght

12.5 km

Categories

High Pressure Water Transport for a Gold Mine.

The Challenge

The engineering company SAXUM had the challenge of designing the main water supply line for Mansfield’s “Lindero Gold Mine” project, which through heap leaching removes and processes mineral.

Given the differences in height (more than 300 meters in total) and the length, a pipe was required that would provide safety to work with high pressures and that can be exposed to the sun without the need to bury it.

Due to the climatic conditions of the area, with low temperatures and strong winds, added to the height (above 4000 m above sea level), a simple and quick solution to install was sought, since otherwise the costs of assembly would be very high.

Pexgol Solution

It was decided to install Pexgol since it is supplied in coils, in this case up to 280 meters in length. Compared to steel and HDPE supplied in 12 or 14 meter lengths, this supply format kept labor and the posibility of failure to a minimum.

Approximately 1,400 meters were installed per day with only three operators and a backhoe. The connections were made by electrofusion couplings.

Related Case Studies

Reduced wear and increased durability in the sand cleaning process at KSB de México.

Improving efficiency in steel foundry with Pexgol

KSB de Mexico
Mexico

 | 

2023
Pexgol’s piping system enabled Nexa Resources to revamp their waste management process, significantly reducing environmental impact.

Enhancing Nexa Resource’s Waste Management Using Pexgol Pipes

Nexa Resources
Brazil

 | 

2023
Installation of Pexgol Pipe in a Formation Water Treatment Plant.

Secondary Injection Water Plant

YPF
Argentina

 | 

2020
Water line feed from wells to mine

Water Lines – High Pressure Water Feed Lines

Yamana Gold, Meridian Mine
Chile

 | 

2012
Pipe installation on a mountain

Meltdown Water Transport

Codelco Andina, TADA 1-2 Project
Chile

 | 

2013
High Pressure Water Transport for a Gold Mine.

High Pressure Water Transport

Mansfield Mine
Argentina

 | 

2019