Skip to content

High Pressure Water Transport

High Pressure Water Transport for a Gold Mine.

Case Study Nº

86

Customer

Mansfield Mine
Argentina

|

2019

Working Conditions

Exposed pipe with repump systems at 21 bar (305 PSI)

Pexgol Pipes

Pexgol 225 mm (8″), class 24, 19, 15 & 12

Application

Water transport

Lenght

12.5 km

Categories

High Pressure Water Transport for a Gold Mine.

The Challenge

The engineering company SAXUM had the challenge of designing the main water supply line for Mansfield’s “Lindero Gold Mine” project, which through heap leaching removes and processes mineral.

Given the differences in height (more than 300 meters in total) and the length, a pipe was required that would provide safety to work with high pressures and that can be exposed to the sun without the need to bury it.

Due to the climatic conditions of the area, with low temperatures and strong winds, added to the height (above 4000 m above sea level), a simple and quick solution to install was sought, since otherwise the costs of assembly would be very high.

Pexgol Solution

It was decided to install Pexgol since it is supplied in coils, in this case up to 280 meters in length. Compared to steel and HDPE supplied in 12 or 14 meter lengths, this supply format kept labor and the posibility of failure to a minimum.

Approximately 1,400 meters were installed per day with only three operators and a backhoe. The connections were made by electrofusion couplings.

Related Case Studies

Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE.

Pexgol Elbow for Slurry Transport

Antioquia Gold
Colombia

 | 

2022
Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

Palm Oil: Transport of Leached Mud

Industria Chiquibul
Guatemala

 | 

2018
Securing the future of gold mining: Newmont Corporation chooses Pexgol for water transport

Newmont’s Water Transportation Revolution with Pexgol Pipes

Newmont Corporation
Argentina

 | 

2018
Slurry transportation with high nickel levels

Leached Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2013
In an engineering challenge, the Pexgol 225 mm (8”) Class 15 pipe proved to be the perfect solution for transporting tailings at the Mina Capela mining complex.

Environmental Protection and Efficiency in Tailings Management

Mina Capella - Grupo Peñoles
Mexico

 | 

2023
Sewage Water Transportation with 300 PPM Hydrogen Peroxide

Sewage Water Transportation

BorsodChem
Hungary

 | 

2011