Open Cast Mine Dewatering

Water Transportation through Shafts

Case Study Nº

39

Customer

Agnico Eagle Pinos Altos Mine
Mexico

|

2017

Working Conditions

300 psi, altitude dierence= 174 m, mine water with 15-20% solids.

Pexgol Pipes

Pexgol SDR 7.4 225×30.8.

Application

Dewatering.

Lenght

225 meters.

Categories

Water Transportation through Shafts

The Challenge

The ground water control system used at Pinos Altos Mine is trough dewatering, which is the method that better adjust to the characteristics of the mine work, furthermore it’s the more efficient and cost-effective if it’s handled the right way.

The fluid transportation associated costs in the mining industry represents an important percentage of the total cost of the operation, consequently the development of work schemes and a hydraulic system optimization, generates important savings on operational costs.

For the pumping system optimization the client designed a pool on level 28, that will gather the runoff water from the superior levels after pumping up to level 22.

Pexgol Solution

For this conduction line a Pexgol pipe was chosen, since it fulfilled the technical features that the job required. Due its ability to be supplied in long length coils, and its capacity to hold 175 meters of water column (249 psi), plus its easy-to-maneuver and installation capabilities (since the pipe was installed through the shafts) and its supplied long sections (which prevents head losses through the joints), the Pexgol pipe was the perfect solution. In addition, the Pexgol pipe roughness coefficient is lower than other pipes, therefore less friction losses and energy savings were encountered.

Related Case Studies

Case Study: Pexgol’s Solution at the Palm Oil Plant.

Efficiency and Durability in Handling Muddy Water

Industrial Aceitera del Casanare
Colombia

 | 

2023
Sewage Water Transportation with 300 PPM Hydrogen Peroxide

Sewage Water Transportation

BorsodChem
Hungary

 | 

2011
Test Of Pexgol Pipes Vs Hdpe Pipes For Brine Transportation

Test: Pexgol vs HDPE for Brine Transportation

YBL
Bolivia

 | 

2017
Replacement of a HDPE Pipe for a Pexgol Pipe

Slurry Transportation

Sabinas Mine
Mexico

 | 

2017
Pan American Energy implements an efficient and sustainable solution for brine transportation.

Fast and Safe Brine Transport in the Salar de Hombre Muerto

Lithos (PAE)
Argentina

 | 

2024
Installation of Pexgol Pipesf for the Drainage of an Underground Mine.

High Pressure Drain in Underground Mine

Ojos del Salado Mine – Lundin Mining
Chile

 | 

2018