Pexgol Elbow for Slurry Transport

Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE.

Case Study Nº

109

Customer

Antioquia Gold
Colombia

|

2022

Working Conditions

Fluid: Sludge | Temperature: 40°C / 104°F

Pexgol Pipes

Pexgol 45° elbow 160 mm, class 15 | GP flanged coupling 160 mm

Application

Slurry transport

Lenght

n/a

Categories

Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE

The Challenge

Antioquia Gold, a Colombian mining company, required continuous maintenance to the HDPE pipe (160 mm PN16) that they used for the discharge to the FALCON 1 gravimetric concentrator, which suffered from constant abrasion problems. It had to be thermo-fused in very short sections to give the necessary radius of curvature in the operation. This pipe had a durability of 1 to 2 months maximum.

Pexgol Solution

Due to its durability, ease of installation (mechanical) and because it does not require maintenance, Antioquia Gold decides to use a Pexgol elbow.

The elbow was installed and after 90 days of testing, the elbow and the connections have maintained hermeticity without fluid loss, maintaining the integrity and initial conditions during the period of operation, when subjected to the expected conditions.

Thanks to the benefits of Pexgol elbows and the versatility of the GP flange coupler, the tolerance of the elbow and its easy handling, the operation cuts were carried out satisfactorily. The elbow was installed by simply aligning the mechanical flanges, making the installation complete in 20 minutes.

Related Case Studies

High-pressure water transport for the Southern Pit in a copper and zinc mine.

High-pressure fluid transport

Minera Antapaccay
Peru

 | 

2023
The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
Transport of Muddy Water (Pome) witha High Content of Organic Load.

Transport of Muddy Water in a Palm Oil Processing Plant

La Gloria
Colombia

 | 

2020
How Pexgol Accelerated the Supply and Installation of a Critical Line.

Comprehensive Water Transportation Solution for Urgent Projects

Madagascar Mining
Madagascar

 | 

2024
Pexgol’s piping system enabled Nexa Resources to revamp their waste management process, significantly reducing environmental impact.

Enhancing Nexa Resource’s Waste Management Using Pexgol Pipes

Nexa Resources
Brazil

 | 

2023
Pexgol pipe was selected for the Assembly of a Muddy Water Transport Line for a Palm Oil Processing Company.

Efficient Choice: PE-X Pipe for the Palm Industry

Extractora Monterrey
Colombia

 | 

2023