Water Transportation
Replacement of Carbon Steel Pipe for a Pexgol Pipe
Case Study Nº
42
Customer
Cargill
Mexico
|
2017
Working Conditions
Work done at -65 meters
Pexgol Pipes
Pexgol 100 mm (4″) SDR 11.
Application
Water transportation.
Lenght
50 meters.
Categories

The Challenge
In the plant “Purina” the water for production is taken from a well.
Originally they used carbon steel pipes to transport the water, which were useful only for a year, then they had to change the pipes since they suffered serious corrosion problems.
This phenomenon happened due to the high sodium content of the groundwater.
Pexgol Solution
The customer required a flexible pipe with a longer service life than carbon steel pipes to maintain a stable operation and minimize sudden stoppages for maintenance operations.
It was, therefore, decided to supply a pipe of 110 mm diameter in a single section which can withstand without any inconvenience the weight of the pump, the cables, the water column and the weight of the pipe.
Related Case Studies
Open Cast Mine Dewatering
Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile
|
2013
Mining Drainage Lines
Lundin Mining – Alcaparosa Mine
Chile
|
2019
From Steel to Pexgol: A Plumbing Upgrade for Tel Aviv’s Gordon Pool
Gordon Pool
Israel
|
2023