Dewatering at an Open Cast Mine

Water Extraction From A Middle Pool To The Exterior Of The Mine

Case Study Nº

30

Customer

Codelco, Ministro Hales Division
Chile

|

2016

Working Conditions

Extreme temperatures (-25° to 40°C).

Pexgol Pipes

Pexgol 160 mm Class 19 (SDR 9).

Application

Water extraction

Lenght

400 m.

Categories

Water Extraction From A Middle Pool To The Exterior Of The Mine

The Challenge

The harsh environmental conditional where Codelco needed to install dewatering lines at the open cast mine, made the engineers opt for a change in their pipe material. They consider Pexgol as an option to decrease the repetitive failures they had with former materials.

Pexgol Solution

A 400 meters Pexgol pipe 160 mm Class 19 was provided, in one section without joints. The Pexgol pipe allowed a quick, reliable and easy installation on the harshest conditions of the open cast mine.

Related Case Studies

Test Of Pexgol Pipes Vs Hdpe Pipes For Brine Transportation

Test: Pexgol vs HDPE for Brine Transportation

YBL
Bolivia

 | 

2017
Dewatering tThrough Shafts for an Underground Lead-Zinc Mine.

Dewatering Through Shafts

Esan Eczacibasi Endustriyel Hammaddeler
Turkey

 | 

2019
Acid liquor line with high levels of abrasion and sedimentation

Abrasive Liquid Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2014
Innovation and improvement in fluid transportation in the oil and gas industry.

Streamlining Effluent Treatment with Pexgol

Pan American Energy
Argentina

 | 

2023
Installation of Buried Pipes to Transport Water on a Mining Road.

Water Transportation on a Mining Road

CODELCO – Andina Mine
Chile

 | 

2019
Transport of acid slurry at high temperatures

Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2012