Condições de Trabalho

Extreme temperatures (-25° to 40°C).

Solução Pexgol

Pexgol 160 mm Class 19 (SDR 9).

Aplicação

Water extraction

Comprimento

400 m.

Categorias

Water Extraction From A Middle Pool To The Exterior Of The Mine

The Challenge

The harsh environmental conditional where Codelco needed to install dewatering lines at the open cast mine, made the engineers opt for a change in their pipe material. They consider Pexgol as an option to decrease the repetitive failures they had with former materials.

Pexgol Solution

A 400 meters Pexgol pipe 160 mm Class 19 was provided, in one section without joints. The Pexgol pipe allowed a quick, reliable and easy installation on the harshest conditions of the open cast mine.

Estudos de Caso Relacionados

Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Hot & Abrasive Potash Brine Processing

Fertilizer Company
Canada

 | 

2017
Corrosion-resistant, lightweight piping for challenging mining environment.

Pexgol Enhances Lithium Brine Well Testing Manifolds

Gaana Servicios Mineros
Argentina

 | 

2024
Moving from PVC to Pexgol: Ensuring Efficiency in Lithium Production

Optimization of Lithium Brine Transportation

Puna Mining
Argentina

 | 

2022
The Robust & Flexible Answer to Constantly Changing Mine Surfaces.

Evolving Mine Operations with Pexgol Piping

Peña Colorada
Mexico

 | 

2023
Water line feed from wells to mine

Mine Dewatering – High Pressure Conditions

Antofagasta Minerals, Michilla Mine
Chile

 | 

2011
Extraction of underground water through wells

Extraction of Underground Water

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2010