Condições de Trabalho

Extreme temperatures (-25° to 40°C).

Solução Pexgol

Pexgol 160 mm Class 19 (SDR 9).

Aplicação

Water extraction

Comprimento

400 m.

Categorias

Water Extraction From A Middle Pool To The Exterior Of The Mine

The Challenge

The harsh environmental conditional where Codelco needed to install dewatering lines at the open cast mine, made the engineers opt for a change in their pipe material. They consider Pexgol as an option to decrease the repetitive failures they had with former materials.

Pexgol Solution

A 400 meters Pexgol pipe 160 mm Class 19 was provided, in one section without joints. The Pexgol pipe allowed a quick, reliable and easy installation on the harshest conditions of the open cast mine.

Estudos de Caso Relacionados

Guaranteeing an efficient water supply with the Pexgol piping solution in the Mendoza-San Juan Highway project.

Streamlining Water Supply in Highway Construction

Chediack / Ceosa
Argentina

 | 

2023
Food Transport Pexgol vs HDPE

Food Transport Pexgol vs HDPE

Marine Farms
Chile

 | 

2017
How Pexgol piping improved the fire network system infrastructure in a paint manufacturing plant.

Pexgol Piping for Fire Network System Expansion

Wall
Argentina

 | 

2023
Pexgol Pipe Installation for the Transport of Water with Solids (Feathers, Bones, Viscera, Etc.)

Transportation of Water with Solids

Kofanor
Mexico

 | 

2022
Transport of high corrosive material from the thickeners to the neutralization plant

Corrosive Material Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2015
Transport of Muddy Water (Pome) witha High Content of Organic Load.

Transport of Muddy Water in a Palm Oil Processing Plant

La Gloria
Colombia

 | 

2020