Dewatering at an Open Cast Mine

Water Extraction From A Middle Pool To The Exterior Of The Mine

Estudo de Caso Nº

30

Cliente

Codelco, Ministro Hales Division
Chile

|

2016

Condições de Trabalho

Extreme temperatures (-25° to 40°C).

Solução Pexgol

Pexgol 160 mm Class 19 (SDR 9).

Aplicação

Water extraction

Comprimento

400 m.

Categorias

Water Extraction From A Middle Pool To The Exterior Of The Mine

The Challenge

The harsh environmental conditional where Codelco needed to install dewatering lines at the open cast mine, made the engineers opt for a change in their pipe material. They consider Pexgol as an option to decrease the repetitive failures they had with former materials.

Pexgol Solution

A 400 meters Pexgol pipe 160 mm Class 19 was provided, in one section without joints. The Pexgol pipe allowed a quick, reliable and easy installation on the harshest conditions of the open cast mine.

Estudos de Caso Relacionados

Test Of Pexgol Pipes Vs Hdpe Pipes For Brine Transportation

Test: Pexgol vs HDPE for Brine Transportation

YBL
Bolivia

 | 

2017
Bridging the Gap between Durability and Functionality in Harsh Processing Environments.

Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport

Syncrude
Canada

 | 

2022
Food Transport Pexgol vs HDPE

Food Transport Pexgol vs HDPE

Marine Farms
Chile

 | 

2017
Water transportation with sulfide and cobalt particles

Water and Sulfide Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2015
Replacement of HDPE Pipe for Pexgol

Slurry Transportation

Tizapa Mine
Mexico

 | 

2015
Química del Rey replaced a corroded steel column with a Pexgol line, achieving a faster, safer, and more durable installation.

Reliable Solution for Deep Wells in Corrosive Environments

Química del Rey
Mexico

 | 

2022