Drainage in Underground Mine

Replacement of a Drainage Line in an Underground Mine.

Case Study Nº

74

Customer

Atacama Kozan
Chile

|

2019

Working Conditions

Underground work

Pexgol Pipes

Pexgol 160 mm (6”), class 10, 15, 19, 24 & 30

Application

Dewatering

Lenght

3573 m / 11722.44 ft

Categories

Replacement of a Drainage Line in an Underground Mine.

The Challenge

Atacama Kozan, a mining company engaged in the production of high-purity copper concentrate in the Atacama region (Chile), required to
change one of the two lines in the mine’s main drainage system. They need a pipeline with a non-invasive installation to make sure the mining operation was able to continue working in the shortest time possible.

Pexgol Solution

The client decided to install 3,573 meters of Pexgol 160 mm pipe in different classes: 10, 15, 19, 24 and 30. They chose to use cross-linked polyethylene due to:

  • Savings in time and costs due to its long-length supply format with fewer joints.
  • Ease of installation, thanks to the flexibility of the pipe that was able to be accommodated without problems in the curves of the interior of the mine.
  • Limited installation times to avoid stopping the mining operation.
  • Cost savings by optimizing and selecting the pipeline laying according to the pressures and hydraulic profile of the project.

Installation was quick and easy, the pipeline was uncoiled entirety and then dragged into the mine. Eight electrofusion joints were made, in addition, on-site consulting was carried out for the electrofusion work.

Related Case Studies

Transport Of Palm Oil Slurry At 95°C.

Transport of Palm Oil Slurry

Loma Fresca
Colombia

 | 

2017
Water Extraction From Deep Wells (150 Meters)

Water Extraction from Wells

Andacollo Mine
Chile

 | 

2015
Installation of a Drainage System in an Open Pit Mine.

Drainage System

BHP Pampa Norte – Cerro Colorado Mine
Chile

 | 

2020
An Outdoor Hydrant and Indoor Sprinklers were installed at Guyana Airport

Water Supply & Fire Extinguisher Line

Cheddi Jagan International Airport
Guyana

 | 

2018
Replacing HDPE pipes with Pexgol allowed Vale to simplify operations, eliminate auxiliary equipment, and achieve a permanent installation under extreme conditions.

Comprehensive Redesign of the PumpingSystem with Pexgol at the Sossego Mine

Vale
Brazil

 | 

2024
Minas Argentinas Replaces HDPE with Pexgol in Its Secondary Leaching Project

Efficient and Safe Irrigation in Secondary Leaching with Pexgol

Minas Argentinas S.A.
Argentina

 | 

2025