Skip to content

Drainage in Underground Mine

Replacement of a Drainage Line in an Underground Mine.

Case Study Nº

74

Customer

Atacama Kozan
Chile

|

2019

Working Conditions

Underground work

Pexgol Pipes

Pexgol 160 mm (6”), class 10, 15, 19, 24 & 30

Application

Dewatering

Lenght

3573 m / 11722.44 ft

Categories

Replacement of a Drainage Line in an Underground Mine.

The Challenge

Atacama Kozan, a mining company engaged in the production of high-purity copper concentrate in the Atacama region (Chile), required to
change one of the two lines in the mine’s main drainage system. They need a pipeline with a non-invasive installation to make sure the mining operation was able to continue working in the shortest time possible.

Pexgol Solution

The client decided to install 3,573 meters of Pexgol 160 mm pipe in different classes: 10, 15, 19, 24 and 30. They chose to use cross-linked polyethylene due to:

  • Savings in time and costs due to its long-length supply format with fewer joints.
  • Ease of installation, thanks to the flexibility of the pipe that was able to be accommodated without problems in the curves of the interior of the mine.
  • Limited installation times to avoid stopping the mining operation.
  • Cost savings by optimizing and selecting the pipeline laying according to the pressures and hydraulic profile of the project.

Installation was quick and easy, the pipeline was uncoiled entirety and then dragged into the mine. Eight electrofusion joints were made, in addition, on-site consulting was carried out for the electrofusion work.

Related Case Studies

In an engineering challenge, the Pexgol 225 mm (8”) Class 15 pipe proved to be the perfect solution for transporting tailings at the Mina Capela mining complex.

Environmental Protection and Efficiency in Tailings Management

Mina Capella - Grupo Peñoles
Mexico

 | 

2023
Installation of Pexgol Pipes to Transport Fish.

Fish Discharge Lines

TASA
Peru

 | 

2018

Categories:

Installation of Pexgol Pipe for the Transport of Abrasive Tailings.

Abrasive Tailings Transport

Pirquitas Mine
Argentina

 | 

2015
Pexgol technology can overcome challenges in shallow well applications, offering an efficient and cost-effective solution for leading companies in the agricultural industry.

Success in Agricultural Desalination: Water Supply Challenges

BerryMex
Mexico

 | 

2019
Replacement of HDPE Pipes For Pe-X to Transport Industrial Treated Water.

Industrial Waste Water to MBR Treatment Facility

Chip Manufacturer
Israel

 | 

2021
Water Extraction From A Middle Pool To The Exterior Of The Mine

Dewatering at an Open Cast Mine

Codelco, Ministro Hales Division
Chile

 | 

2016