Skip to content

Drainage in Underground Mine

Replacement of a Drainage Line in an Underground Mine.

Case Study Nº

74

Customer

Atacama Kozan
Chile

|

2019

Working Conditions

Underground work

Pexgol Pipes

Pexgol 160 mm (6”), class 10, 15, 19, 24 & 30

Application

Dewatering

Lenght

3573 m / 11722.44 ft

Categories

Replacement of a Drainage Line in an Underground Mine.

The Challenge

Atacama Kozan, a mining company engaged in the production of high-purity copper concentrate in the Atacama region (Chile), required to
change one of the two lines in the mine’s main drainage system. They need a pipeline with a non-invasive installation to make sure the mining operation was able to continue working in the shortest time possible.

Pexgol Solution

The client decided to install 3,573 meters of Pexgol 160 mm pipe in different classes: 10, 15, 19, 24 and 30. They chose to use cross-linked polyethylene due to:

  • Savings in time and costs due to its long-length supply format with fewer joints.
  • Ease of installation, thanks to the flexibility of the pipe that was able to be accommodated without problems in the curves of the interior of the mine.
  • Limited installation times to avoid stopping the mining operation.
  • Cost savings by optimizing and selecting the pipeline laying according to the pressures and hydraulic profile of the project.

Installation was quick and easy, the pipeline was uncoiled entirety and then dragged into the mine. Eight electrofusion joints were made, in addition, on-site consulting was carried out for the electrofusion work.

Related Case Studies

Pvc Pipe Replacement by Pexgol

Transportation of sodium sulfide

Magnelec S.A. de C.V.
Mexico

 | 

2018
Moving from PVC to Pexgol: Ensuring Efficiency in Lithium Production

Optimization of Lithium Brine Transportation

Puna Mining
Argentina

 | 

2022
Drainage in Underground Mine with Slopes Between 40° and 90°.

Water Drainage in Underground Mine

NEMISA Mine
Mexico

 | 

2018
Cement Slurry Injection to an Underground Mine

Backfill

Aguilar Mine
Argentina

 | 

2015
Transport of high corrosive material from the thickeners to the neutralization plant

Corrosive Material Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2015
Guaranteeing an efficient water supply with the Pexgol piping solution in the Mendoza-San Juan Highway project.

Streamlining Water Supply in Highway Construction

Chediack / Ceosa
Argentina

 | 

2023