Installation of Pexgol Pipes for a Free Chlorine Potable Water Supply.

Case Study Nº

94

Customer

Rabin Medical Center
Israel

|

2020

Working Conditions

Temperature: 4° to 85°C | Pressure: 6 bar

Pexgol Pipes

Pexgol CL+ 16 mm – 75 mm class 24

Application

Free Chlorine Potable Water Supply

Lenght

1000 m

Categories

Installation of Pexgol Pipes for a Free Chlorine Potable Water Supply.

The Challenge

As one of the most major and central medical institutions in Israel, “Rabin Medical Center” must meet the most severe international health standards. Free Chlorine, if used to sterilize a potable water supply, may lead to Chlorine corrosion, and could even rupture pipes and infrastructure. As little as 0.3 ppm of Chlorine in the water system will lead to high wear and degradation and necessitate frequent replacements.

Pexgol Solution

Pexgol CL+ has proven durability to free Chlorine in a concentration between 0.3-0.5 ppm and working pressures up to 6 bar. By installing Pexgol CL+ in a potable water system, “Rabin Medical Center” can continue to insure a clean and safe supply of water to the hospital.

Related Case Studies

Installation of a Drainage System in an Open Pit Mine.

Drainage System

BHP Pampa Norte – Cerro Colorado Mine
Chile

 | 

2020
Dry Gas Line for Pump Activation.

Dry Gas Transportation

ExxonMobil
Argentina

 | 

2020
Installation of Pexgol Pipes for Transporting Hot Water.

Hot Water Supply

Hilton
Israel

 | 

2020
The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Improvement in Brine Management through Pexgol Piping

Sales de Jujuy
Argentina

 | 

2023
Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Installation of Buried Pipes to Transport Water on a Mining Road.

Water Transportation on a Mining Road

CODELCO – Andina Mine
Chile

 | 

2019