Skip to content

Corrosive Material Transportation

Transport of high corrosive material from the thickeners to the neutralization plant

Case Study Nº

23

Customer

Moa Nickel S.A. Sherritt
Cuba

|

2015

Working Conditions

70° C, 11 bars.

Pexgol Pipes

Pexgol 500 mm, Class 15 and Pexgol 450 mm, Class 15.

Application

Transportation of corrosive material.

Lenght

150 m.

Categories

Transport of high corrosive material from the thickeners to the neutralization plant

The Challenge

Moa Nickel required to transport high corrosive material from the thickeners to the neutralization plant tanks. Originally, they used to do it through a 18 and 16 inches carbon steel line (A53, Gr.B, Sch10), with welded joints and 1/4” rubber lined. The pipe consisted in short pipe sections, 6 meters long each one, approximately 150 meters total length. It was used until it was practically destroyed as a consequence of the corrosion and wear. The engineering team decided that it needed to be replaced before it could affect the production.

Pexgol Solution

Golan presented a quick-to-install solution for the complete substitution of the line. The design included standard and special Pexgol fittings, elbows, Tee instruments and more than 150 meters of pipe. The Pexgol pipe was installed in the same spot as the former carbon steel pipe, improving the supports.

The former carbon steel pipe was 50% more expensive than Pexgol, which also was more convenient and easy to install, saving time and money for its installation.

 

Pipe TypePexgol Cost vs OthersPexgol Total Investment Costs vs Others
Rubbed steel A53 Gr, B Sch. 201:1.41:2
Stainless steel 316L, Sch. 201:21:3
Titanium B862, Gr.2, 3 mm thk1:2.31:3.2
Polypropylene PP-H, SDR 171:3.81:4.2

Related Case Studies

Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

Cold Water Distribution for External Cooler System

Chip Manufacturer
Israel

 | 

2022
Replacement of HDPE Pipes For Pe-X to Transport Industrial Treated Water.

Industrial Waste Water to MBR Treatment Facility

Chip Manufacturer
Israel

 | 

2021
Water Drainage From the Inside of an Underground Mine

Water Drainage at an Underground Mine

El Peñón Yamana Gold, Meridian Mine
Chile

 | 

2016
The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
Changing carbon steel for efficiency: Pexgol PE-X pipes in Aconcagua Energía

Elevating Efficiency in Hydrocarbon Exploitation

Aconcagua Energía
Argentina

 | 

2023
Installation of Buried Pipes to Transport Water on a Mining Road.

Water Transportation on a Mining Road

CODELCO – Andina Mine
Chile

 | 

2019