Groundwater Transportation

Groundwater Transportation With Ph Low Levels

Case Study Nº

29

Customer

Grupo México, Buena Vista del Cobre Mine
Mexico

|

2015

Working Conditions

Underground work (-250 m).

Pexgol Pipes

Pexgol 90 mm (SDR 7.4).

Application

Water transportation

Lenght

200 m.

Categories

Groundwater Transportation With Ph Low Levels

The Challenge

At “Buena Vista del Cobre” Mine the process water was extracted from deep wells. Formerly they worked with stainless steel pipes 316 with 9 months of operational lifetime that required to be replaced due to the corrosion, as a consequence of the low pH (between 1.5 and 2.5) from the groundwater.

Pexgol Solution

The client required a more flexible pipe, with longer operational lifetime than the steel, and minimize the stops at the plant. Therefore, a 3 inch Pexgol pipe was installed in one section, holding the weight of the pump, the cables, the water column and the pipe itself. The new pipe operational lifetime is 50 years.

The client received not only a durable pipe but also a complete solution including fittings for the pump and the discharge head. For a 3 inch 250 meter steel pipe, it would require more than 40 thread joints.

With Pexgol it only took 2 joints. This operation with a steel pipe it would cost $22.000 USD, when a Pexgol operation cost just a third of it. Plus the savings the client got from avoiding to stop the production for the failures.

Related Case Studies

Hot sylvinite leach at 114°C/237°F

Mineral Processing – Potash Processing Plant

ICL group, Dead Sea Works
Israel

 | 

1987
Improving the efficiency of salmon farming with the superior solution of Pexgol pipes.

Pexgol’s Pipe Solution Enhances Salmon Farming

Mowi
Chile

 | 

2021
Installation Of Pexgol Hanging Pipes In Underground Mine

Underground Mine Dewatering

Codelco Chuquicamata
Chile

 | 

2017
Pexgol Pipe Installation for the Transport of Cyanide Water.

Transport of Cyanide Water

Equinox Gold
Mexico

 | 

2022
Slurry transportation with high nickel levels

Leached Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2013
Guaranteeing an efficient water supply with the Pexgol piping solution in the Mendoza-San Juan Highway project.

Streamlining Water Supply in Highway Construction

Chediack / Ceosa
Argentina

 | 

2023