Skip to content

High Pressure Potable Water Line

High Pressure potable water line

Case Study Nº

17

Customer

Antofagasta Minerals, Pelambres Mine
Chile

|

2014

Working Conditions

Gravity flow on harsh ground at 3,400 m altitude. 300 meters elevation difference gravity flow.

Pexgol Pipes

Insulated Pexgol pipe 140 cl 50 (SDR 4.3) polyurethane insulation / Flexwell-Pex 140×32.5/233.

Application

Safe water transportation.

Lenght

300 m.

Categories

High Pressure potable water line

The Challenge

“Pelambres” Mine required to install a safe water line to their new truck garage. The ground were the pipe needed to be installed was very complex with steep slopes.

The mine considered installing carbon steel pipes, but under those complicate conditions, the last 300 meter section was a very severe problem for the installation crew. The original plan considered 60 days for the assembly of that section.

Pexgol Solution

A pre-isolated Pexgol pipe was installed (Flexwell-Pex 140×32.5//233), that substituted the last 300 meters section of the carbon steel pipe.

The Pexgol pipe was provided in three long sections and welded in the ground by the Golan team, who also instructed the mine workers and the contractor.

The three sections were de-coiled and were welded by electro-fusion.

In the joints the polyurethane was replaced and reinforced.

The original schedule plan estimated 60 days for the installation, but with Pexgol it took only 15 days instead, with an optimal use of resources.

Related Case Studies

Installation of Pexgol Pipes for Transporting Hot Water.

Hot Water Supply

Hilton
Israel

 | 

2020
Guaranteeing an efficient water supply with the Pexgol piping solution in the Mendoza-San Juan Highway project.

Streamlining Water Supply in Highway Construction

Chediack / Ceosa
Argentina

 | 

2023
Trial Demonstrates Superior Wear Resistance in Sea Water + Ash Slurry Conditions.

Unmatched Durability in Harsh Slurry: Pexgol Outperforms Steel

Tata Power
India

 | 

2023
Pexgol Pipe Installation for Open Pit Mine Drainage.

Efficient Open Pit Mine Drainage

BHP Escondida Mine
Chile

 | 

2022
A high-precision maneuver enabled the complete assembly of the system in record time, ensuring safety and operational continuity.

Pexgol Overcomes Extreme Dewatering Conditions in La Ciénega

Fresnillo Plc.
Mexico

 | 

2025
Installation of 1000 Meters of PE-X Pipe for an Underground Mine.

Mining Drainage Lines

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019