Skip to content

High Pressure Potable Water Line

High Pressure potable water line

Case Study Nº

17

Customer

Antofagasta Minerals, Pelambres Mine
Chile

|

2014

Working Conditions

Gravity flow on harsh ground at 3,400 m altitude. 300 meters elevation difference gravity flow.

Pexgol Pipes

Insulated Pexgol pipe 140 cl 50 (SDR 4.3) polyurethane insulation / Flexwell-Pex 140×32.5/233.

Application

Safe water transportation.

Lenght

300 m.

Categories

High Pressure potable water line

The Challenge

“Pelambres” Mine required to install a safe water line to their new truck garage. The ground were the pipe needed to be installed was very complex with steep slopes.

The mine considered installing carbon steel pipes, but under those complicate conditions, the last 300 meter section was a very severe problem for the installation crew. The original plan considered 60 days for the assembly of that section.

Pexgol Solution

A pre-isolated Pexgol pipe was installed (Flexwell-Pex 140×32.5//233), that substituted the last 300 meters section of the carbon steel pipe.

The Pexgol pipe was provided in three long sections and welded in the ground by the Golan team, who also instructed the mine workers and the contractor.

The three sections were de-coiled and were welded by electro-fusion.

In the joints the polyurethane was replaced and reinforced.

The original schedule plan estimated 60 days for the installation, but with Pexgol it took only 15 days instead, with an optimal use of resources.

Related Case Studies

Dewatering With Low Ph Levels

Open Cast Mine Dewatering

Arcelor Mittal Mine
Mexico

 | 

2016
Reducing maintenance and increasing safety in hydraulic backfill operations.

Pexgol Simplifies Slurry Transportation at Buriticá Mine

Zijin - Continental Gold
Colombia

 | 

2023
Work with High Pressures and Extreme Ambient Temperature

Water Transport in Copper Mine

Zaldivar SPA Mine
Chile

 | 

2018
Replacement of Carbon Steel Pipes by Pexgol for Fire Fighting Network.

Water Transport for Fire Network

Profertil
Argentina

 | 

2022
Performance evaluation of Pexgol lining under extreme service conditions.

Durable Solution Against Abrasion in Production Facilities: Pexgol at YPF

YPF
Argentina

 | 

2018
Pan American Energy implements an efficient and sustainable solution for brine transportation.

Fast and Safe Brine Transport in the Salar de Hombre Muerto

Lithos (PAE)
Argentina

 | 

2024