Skip to content

High Pressure Potable Water Line

High Pressure potable water line

Case Study Nº

17

Customer

Antofagasta Minerals, Pelambres Mine
Chile

|

2014

Working Conditions

Gravity flow on harsh ground at 3,400 m altitude. 300 meters elevation difference gravity flow.

Pexgol Pipes

Insulated Pexgol pipe 140 cl 50 (SDR 4.3) polyurethane insulation / Flexwell-Pex 140×32.5/233.

Application

Safe water transportation.

Lenght

300 m.

Categories

High Pressure potable water line

The Challenge

“Pelambres” Mine required to install a safe water line to their new truck garage. The ground were the pipe needed to be installed was very complex with steep slopes.

The mine considered installing carbon steel pipes, but under those complicate conditions, the last 300 meter section was a very severe problem for the installation crew. The original plan considered 60 days for the assembly of that section.

Pexgol Solution

A pre-isolated Pexgol pipe was installed (Flexwell-Pex 140×32.5//233), that substituted the last 300 meters section of the carbon steel pipe.

The Pexgol pipe was provided in three long sections and welded in the ground by the Golan team, who also instructed the mine workers and the contractor.

The three sections were de-coiled and were welded by electro-fusion.

In the joints the polyurethane was replaced and reinforced.

The original schedule plan estimated 60 days for the installation, but with Pexgol it took only 15 days instead, with an optimal use of resources.

Related Case Studies

Extraction of underground water through wells

Extraction of Underground Water

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2010
Pexgol Pipe for the Transport of Fluorosilicic Acid.

Fluorosilicic Acid Transport

Phosphate Mine – ICL Rotem
Israel

 | 

1995
Hot Caustic Line Replacement in Paper Mill

Pulp & Paper Mill

Svetlogorskiy Mill
Russia

 | 

2015
Pipe installation on a mountain

Meltdown Water Transport

Codelco Andina, TADA 1-2 Project
Chile

 | 

2013
Scale build up reduction - highly concentrated lime solution

Process Water – Brine Transportation

SQM Nueva Victoria-Iquique
Chile

 | 

2010
Installation of a Borehole with Pipe in Sections for Reduced Space.

Installation of Water Well in Reduced Space

Mekorot
Israel

 | 

2020