Skip to content

High Pressure Potable Water Line

High Pressure potable water line

Case Study Nº

17

Customer

Antofagasta Minerals, Pelambres Mine
Chile

|

2014

Working Conditions

Gravity flow on harsh ground at 3,400 m altitude. 300 meters elevation difference gravity flow.

Pexgol Pipes

Insulated Pexgol pipe 140 cl 50 (SDR 4.3) polyurethane insulation / Flexwell-Pex 140×32.5/233.

Application

Safe water transportation.

Lenght

300 m.

Categories

High Pressure potable water line

The Challenge

“Pelambres” Mine required to install a safe water line to their new truck garage. The ground were the pipe needed to be installed was very complex with steep slopes.

The mine considered installing carbon steel pipes, but under those complicate conditions, the last 300 meter section was a very severe problem for the installation crew. The original plan considered 60 days for the assembly of that section.

Pexgol Solution

A pre-isolated Pexgol pipe was installed (Flexwell-Pex 140×32.5//233), that substituted the last 300 meters section of the carbon steel pipe.

The Pexgol pipe was provided in three long sections and welded in the ground by the Golan team, who also instructed the mine workers and the contractor.

The three sections were de-coiled and were welded by electro-fusion.

In the joints the polyurethane was replaced and reinforced.

The original schedule plan estimated 60 days for the installation, but with Pexgol it took only 15 days instead, with an optimal use of resources.

Related Case Studies

The transition to the Pexgol piping system allowed Paladini to ensure a smooth and efficient wastewater transport process for their agricultural irrigation.

Pexgol Pipes for Efficient Wastewater Transport

Paladini
Argentina

 | 

2022
Replacement of a HDPE Pipe for a Pexgol Pipe

Slurry Transportation

Sabinas Mine
Mexico

 | 

2017
Drainage in Underground Mine with Slopes Between 40° and 90°.

Water Drainage in Underground Mine

NEMISA Mine
Mexico

 | 

2018
Overcoming Corrosion Challenges in the Oil Industry

Overcoming Corrosion Challenges in the Oil Industry

Petróleos Sudamericanos
Argentina

 | 

2023
In an engineering challenge, the Pexgol 225 mm (8”) Class 15 pipe proved to be the perfect solution for transporting tailings at the Mina Capela mining complex.

Environmental Protection and Efficiency in Tailings Management

Mina Capella - Grupo Peñoles
Mexico

 | 

2023
Dewatering tThrough Shafts for an Underground Lead-Zinc Mine.

Dewatering Through Shafts

Esan Eczacibasi Endustriyel Hammaddeler
Turkey

 | 

2019