Leached Slurry Transportation

Slurry transportation with high nickel levels

Case Study Nº

18

Customer

Moa Nickel S.A. Sherritt
Cuba

|

2013

Working Conditions

Extreme transport temperature (110°C).

Pexgol Pipes

Pexgol 500 mm, Class 15 & Pexgol 355 mm, Class 15.

Application

Slurry transportation.

Lenght

350 m.

Categories

Slurry transportation with high nickel levels

The Challenge

Moa Nickel used to transport leached slurry from the tubular reactors to the CCD thickener feed line. This process caused several issues on different pipe materials. The transported fluid was composed by:

  • 28-32 g/l acid
  • 1,00 g/l N
  • 0,54 g/l Co
  • 1,00 g/l Fe
  • 21,00 g/l SO4
  • 30,0 g/l free acids
  • Solids: 0,086% Ni, 0,013% Co, 46,00% Fe

Previously, titanium Sch20 pipes were installed, but if suffered deformations and it needed to be repaired constantly. The titanium pipe was replaced for a stainless steel pipe 316 Sch40, and it lasted 8 years and it finally required to be replaced because it presented wear issues.

Pexgol Solution

Golan provided 11.8 meters of pipes sections with mechanical joins that could resist corrosion, high temperatures and wear with no effort.

Regarding the prices per meter, installation costs and maintenance, versus stainless steel and titanium pipes, Pexgol proved to be the most convenient option.

Related Case Studies

Installation of a Drainage System between Dams in a Copper Mine.

Water Transport Between Dams

CODELCO – El Teniente Mine
Chile

 | 

2019
Delivering Durability and Flexibility for a Sustainable Approach to Space Access.

Pioneering Space Launches with Ground-breaking Piping Solutions

SpinLaunch
USA

 | 

2021
Transformation in the logistics of formation water.

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

Aconcagua Energía
Argentina

 | 

2023
A Two-Phase Installation for High-Temperature Hot Water Supply & Return.

Scaling Up Efficiency: District Energy at Penn State Harrisburg

Penn State University - Harrisburg
USA

 | 

2021
Pexgol Pipe Installation for Open Pit Mine Drainage.

Efficient Open Pit Mine Drainage

BHP Escondida Mine
Chile

 | 

2022
Replacing steel pipes suffering from sediment formation

Transportation of Ore Slurry

RUSAL, aluminum factory
Russia

 | 

2012