Skip to content

Meltdown Water Transport

Pipe installation on a mountain

Case Study Nº

16

Customer

Codelco Andina, TADA 1-2 Project
Chile

|

2013

Working Conditions

Complex & harsh ground, 300 m altitude.

Pexgol Pipes

Pexgol 315 mm, Class 15 (SDR 11).

Application

Water transportation.

Lenght

3,300 m.

Categories

Pipe installation on a mountain

The Challenge

Codelco needed to transport meltdown water downhill at Andes Mountain range.

The water pipes installation was a big risk for the team, as well as huge workforce with short time schedules.

Pexgol Solution

Using hoses seemed to be the solution, but the complexity of its installation made the client decided to use Pexgol in long sections instead.

The installation was simplified by the use of Pexgol long sections.

The pipes were unrolled from it coils and jointed trough electro-fusion, to be dragged and mapped out according to the project.

The installation was done in perfect timing with an optimal performance.

Related Case Studies

Successful outcome in pilot test for SCT Discharge Line with Pexgol.

Advanced piping solutions for handlingscaling fluids

Barrick Gold
Dominican Republic

 | 

2023
Pexgol and Fresnillo: Allies in innovative piping solutions for mining.

Safety and durability: The heart of our solutions

Minera Fresnillo
Mexico

 | 

2021
Replacement of a HDPE Pipe for a Pexgol Pipe

Compressed Air Transportation

Saucito S.A. de C.V. Mine
Mexico

 | 

2017
Guaranteeing an efficient water supply with the Pexgol piping solution in the Mendoza-San Juan Highway project.

Streamlining Water Supply in Highway Construction

Chediack / Ceosa
Argentina

 | 

2023
How Pexgol piping improved the fire network system infrastructure in a paint manufacturing plant.

Pexgol Piping for Fire Network System Expansion

Wall
Argentina

 | 

2023
How Pexgol Accelerated the Supply and Installation of a Critical Line.

Comprehensive Water Transportation Solution for Urgent Projects

Madagascar Mining
Madagascar

 | 

2024