Meltdown Water Transport

Pipe installation on a mountain

Case Study Nº

16

Customer

Codelco Andina, TADA 1-2 Project
Chile

|

2013

Working Conditions

Complex & harsh ground, 300 m altitude.

Pexgol Pipes

Pexgol 315 mm, Class 15 (SDR 11).

Application

Water transportation.

Lenght

3,300 m.

Categories

Pipe installation on a mountain

The Challenge

Codelco needed to transport meltdown water downhill at Andes Mountain range.

The water pipes installation was a big risk for the team, as well as huge workforce with short time schedules.

Pexgol Solution

Using hoses seemed to be the solution, but the complexity of its installation made the client decided to use Pexgol in long sections instead.

The installation was simplified by the use of Pexgol long sections.

The pipes were unrolled from it coils and jointed trough electro-fusion, to be dragged and mapped out according to the project.

The installation was done in perfect timing with an optimal performance.

Related Case Studies

Pexgol’s chemical resistance and flexibility outperform HDPE in demanding leach pad operations.

Greater Efficiency and Safety in Leaching with Pexgol Pipes

Barrick Gold Corp.
Argentina

 | 

2025
Corrosion-resistant, lightweight piping for challenging mining environment.

Pexgol Enhances Lithium Brine Well Testing Manifolds

Gaana Servicios Mineros
Argentina

 | 

2024
Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

Palm Oil: Transport of Leached Mud

Industria Chiquibul
Guatemala

 | 

2018
Profertil and the Adaptation to New Chemical Processes with Pexgol.

Efficient Implementation of NaOH Drainage Systems

Pluspetrol
Argentina

 | 

2023
Pexgol pipe was selected for the Assembly of a Muddy Water Transport Line for a Palm Oil Processing Company.

Efficient Choice: PE-X Pipe for the Palm Industry

Extractora Monterrey
Colombia

 | 

2023
Replacement of a HDPE Pipe for a Pexgol Pipe

Compressed Air Transportation

Saucito S.A. de C.V. Mine
Mexico

 | 

2017