Skip to content

Open Cast Mine Dewatering

Dewatering With Low Ph Levels

Case Study Nº

34

Customer

Arcelor Mittal Mine
Mexico

|

2016

Working Conditions

Pressure 400 Psi; height difference: 220 m; specific weight 1.15 t/m3; solids 15-20%.

Pexgol Pipes

Pexgol 8” (225 mm).

Application

Dewatering

Lenght

Sections of 280 m.

Categories

Dewatering With Low Ph Levels

The Challenge

Arcerlor Mittal required to dewater their open cast mine, due to the contamination produced by the low pH levels of the water.

The open cast was 220 meters depth with an 80° slope. From the client point of view, installing a regular pipe would involve doing more than 22 joints, on a harsh ground that was also dangerous for the people that work there. In addition, a regular pipe might need to be supported every 12 meters so it will not collapse due to its own weight.

Pexgol Solution

Pexgol pipes were the optimal solution for this project, because it can be supplied in long lengths coils that makes the whole installation easier.

Pexgol is also known for its stress resistance, Pexgol’s crosslinking piping solution can withstand high amounts of axial and radial stresses, it only stretches up to 2% of its own length and it is capable to hold its own weight plus the water column.

Due to it great flexibility, the coil was uncoiled hundreds of meters away from the installation place, and it was dragged after to the right spot.

In order to descend the pipe through the open cast, it required only chains and a backhoe to hold it. Arcelor Mittal was very satisfied with the installation process, which was simple, and from their point of view, impossible to do it with other type of pipe.

Related Case Studies

EMESA Optimizes Formation Water Transportation in Mendoza.

Pexgol’s Solution in Secondary Recovery for EMESA

EMESA
Argentina

 | 

2023
Test Installation for Transporting Silica Sand.

Transport of Silica Arena: HDPE vs Pexgol

Covia Corp
Mexico

 | 

2019
Installation of Buried Pipes to Transport Water on a Mining Road.

Water Transportation on a Mining Road

CODELCO – Andina Mine
Chile

 | 

2019
Replacement Of PVC Piping for PE-X in a Industrial Heating System.

Transport of Hot Air for Advanced Agriculture

Teva Post
Israel

 | 

2022
Transport Of Palm Oil Slurry At 95°C.

Transport of Palm Oil Slurry

Loma Fresca
Colombia

 | 

2017
Transformation in the logistics of formation water.

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

Aconcagua Energía
Argentina

 | 

2023