Skip to content

Palm Oil: Transport of Leached Mud

Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

Case Study Nº

53

Customer

Industria Chiquibul
Guatemala

|

2018

Working Conditions

Muddy water at 90°C, 2 bar pressure

Pexgol Pipes

Pexgol 200 mm (8″) Class 15

Application

Transport of Leached Mud

Lenght

934 m

Categories

Industria Chiquibul
Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

The Challenge

Industria Chiquibul S.A. is an Agro-Industrial project focused on the sowing of African palm and the extraction of its oils. When the oil is processed, there are acid residues (pH 1) which, in addition to being very abrasive by the process itself, are at temperatures between 90° and 100°C.

Chiquibul required to transport this mud to the oxidation lagoons in order to finish the process of recycling the remaining material. Initially, this transport was carried out (in the vicinity of the process plant) with a carbon steel pipe, but it suffered great corrosion problems after only one year of work.

As the production grew, they needed to enlarge the line, and given the operating conditions and the complexity of the land (through a jungle area), Chiquibul decided to change the pipe material.

Pexgol Solution

Chiquibul analyzed different pipe materials, and given Pexgol’s ability to withstand high temperatures and its great chemical resistance, it was chosen for the change. Likewise, they analyzed the installation costs and detected that to make the installation with steel more than 75 unions and a large investment in supports would have been required. In contrast, the PE-X could be supplied in continuous 300 m sections, so the number of joints was reduced to only 3. Also the PE-X pipe could be installed at ground level, without having to make a big investment in supports.

The installation was faster than scheduled, only 4 operators were used, a backhoe in a period of 3 days. The connections used were flanged couplers provided by Pexgol, so only one jig and a set of tightening wrenches were used.

Related Case Studies

Installation of a drainage system between a well and a mining dam.

Drinking Water on Sloping Terrain

AquaMag
Colombia

 | 

2019

Categories:

Groundwater Transportation With Ph Low Levels

Groundwater Transportation

Grupo México, Buena Vista del Cobre Mine
Mexico

 | 

2015
Installation of a Drainage System in an Open Pit Mine.

Drainage System

BHP Pampa Norte – Cerro Colorado Mine
Chile

 | 

2020
The Original Design for a Wastewater Treatment Plant included Stainless Steel Pipes, but after discovering the Superior Capabilities of Pexgol Pipes, the Entire Facility was Switched Over.

New Wastewater Treatment Plant with Pexgol Pipes

Wastewater Treatment Plant
Israel

 | 

2022
Case Study: Pexgol’s Solution at the Palm Oil Plant.

Efficiency and Durability in Handling Muddy Water

Industrial Aceitera del Casanare
Colombia

 | 

2023
The innovative solution from Pexgol for Anglo American Peru’s piping challenges.

Navigating extreme conditions with Pexgol’s PE-X pipes

Anglo American Perú
Peru

 | 

2023