Skip to content

Palm Oil: Transport of Leached Mud

Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

Estudo de Caso Nº

53

Cliente

Industria Chiquibul
Guatemala

|

2018

Condições de Trabalho

Muddy water at 90°C, 2 bar pressure

Solução Pexgol

Pexgol 200 mm (8″) Class 15

Aplicação

Transport of Leached Mud

Comprimento

934 m

Categorias

Industria Chiquibul
Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

The Challenge

Industria Chiquibul S.A. is an Agro-Industrial project focused on the sowing of African palm and the extraction of its oils. When the oil is processed, there are acid residues (pH 1) which, in addition to being very abrasive by the process itself, are at temperatures between 90° and 100°C.

Chiquibul required to transport this mud to the oxidation lagoons in order to finish the process of recycling the remaining material. Initially, this transport was carried out (in the vicinity of the process plant) with a carbon steel pipe, but it suffered great corrosion problems after only one year of work.

As the production grew, they needed to enlarge the line, and given the operating conditions and the complexity of the land (through a jungle area), Chiquibul decided to change the pipe material.

Pexgol Solution

Chiquibul analyzed different pipe materials, and given Pexgol’s ability to withstand high temperatures and its great chemical resistance, it was chosen for the change. Likewise, they analyzed the installation costs and detected that to make the installation with steel more than 75 unions and a large investment in supports would have been required. In contrast, the PE-X could be supplied in continuous 300 m sections, so the number of joints was reduced to only 3. Also the PE-X pipe could be installed at ground level, without having to make a big investment in supports.

The installation was faster than scheduled, only 4 operators were used, a backhoe in a period of 3 days. The connections used were flanged couplers provided by Pexgol, so only one jig and a set of tightening wrenches were used.

Estudos de Caso Relacionados

Installation of 3000 Meters Of PE-X Pipe for an Underground Mine.

Drainage Lines in Underground Mine

Lundin Mining – Candelaria Norte Mine
Chile

 | 

2020
Acid liquor line with high levels of abrasion and sedimentation

Abrasive Liquid Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2014
An Outdoor Hydrant and Indoor Sprinklers were installed at Guyana Airport

Water Supply & Fire Extinguisher Line

Cheddi Jagan International Airport
Guyana

 | 

2018
Transportation of water with solids from an open cast mine

Open Cast Mine Dewatering

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2013
Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE.

Pexgol Elbow for Slurry Transport

Antioquia Gold
Colombia

 | 

2022
Installation Oof Pexgol Pipes through a Chimney for Compressed Air.

Transport of Compressed Air for Underground Mine

HMC Gold
Chile

 | 

2021