Palm Oil: Transport of Leached Mud
Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon
Estudo de Caso Nº
53
Cliente
|
Condições de Trabalho
Solução Pexgol
Aplicação
Comprimento
Categorias
The Challenge
Industria Chiquibul S.A. is an Agro-Industrial project focused on the sowing of African palm and the extraction of its oils. When the oil is processed, there are acid residues (pH 1) which, in addition to being very abrasive by the process itself, are at temperatures between 90° and 100°C.
Chiquibul required to transport this mud to the oxidation lagoons in order to finish the process of recycling the remaining material. Initially, this transport was carried out (in the vicinity of the process plant) with a carbon steel pipe, but it suffered great corrosion problems after only one year of work.
As the production grew, they needed to enlarge the line, and given the operating conditions and the complexity of the land (through a jungle area), Chiquibul decided to change the pipe material.
Pexgol Solution
Chiquibul analyzed different pipe materials, and given Pexgol’s ability to withstand high temperatures and its great chemical resistance, it was chosen for the change. Likewise, they analyzed the installation costs and detected that to make the installation with steel more than 75 unions and a large investment in supports would have been required. In contrast, the PE-X could be supplied in continuous 300 m sections, so the number of joints was reduced to only 3. Also the PE-X pipe could be installed at ground level, without having to make a big investment in supports.
The installation was faster than scheduled, only 4 operators were used, a backhoe in a period of 3 days. The connections used were flanged couplers provided by Pexgol, so only one jig and a set of tightening wrenches were used.
Estudos de Caso Relacionados
Drainage Lines in Underground Mine
|
Water Supply & Fire Extinguisher Line
|
Open Cast Mine Dewatering
|
Transport of Compressed Air for Underground Mine
|