Skip to content

Palm Oil: Transport of Leached Mud

Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

Estudo de Caso Nº

53

Cliente

Industria Chiquibul
Guatemala

|

2018

Condições de Trabalho

Muddy water at 90°C, 2 bar pressure

Solução Pexgol

Pexgol 200 mm (8″) Class 15

Aplicação

Transport of Leached Mud

Comprimento

934 m

Categorias

Industria Chiquibul
Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

The Challenge

Industria Chiquibul S.A. is an Agro-Industrial project focused on the sowing of African palm and the extraction of its oils. When the oil is processed, there are acid residues (pH 1) which, in addition to being very abrasive by the process itself, are at temperatures between 90° and 100°C.

Chiquibul required to transport this mud to the oxidation lagoons in order to finish the process of recycling the remaining material. Initially, this transport was carried out (in the vicinity of the process plant) with a carbon steel pipe, but it suffered great corrosion problems after only one year of work.

As the production grew, they needed to enlarge the line, and given the operating conditions and the complexity of the land (through a jungle area), Chiquibul decided to change the pipe material.

Pexgol Solution

Chiquibul analyzed different pipe materials, and given Pexgol’s ability to withstand high temperatures and its great chemical resistance, it was chosen for the change. Likewise, they analyzed the installation costs and detected that to make the installation with steel more than 75 unions and a large investment in supports would have been required. In contrast, the PE-X could be supplied in continuous 300 m sections, so the number of joints was reduced to only 3. Also the PE-X pipe could be installed at ground level, without having to make a big investment in supports.

The installation was faster than scheduled, only 4 operators were used, a backhoe in a period of 3 days. The connections used were flanged couplers provided by Pexgol, so only one jig and a set of tightening wrenches were used.

Estudos de Caso Relacionados

Pan American Energy implements an efficient and sustainable solution for brine transportation.

Fast and Safe Brine Transport in the Salar de Hombre Muerto

Lithos (PAE)
Argentina

 | 

2024
Transformation in the logistics of formation water.

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

Aconcagua Energía
Argentina

 | 

2023
Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Hot & Abrasive Potash Brine Processing

Fertilizer Company
Canada

 | 

2017
Optimization of Water Systems in the Energy Industry.

“Threading” Pexgol Pipes

Pluspetrol
Argentina

 | 

2023
Installation of a Pexgol Line 200 Meters Deep at an Underground Mine

Transport of Compressed Air

Meridian Mine – Faena El Peñón
Chile

 | 

2018
Water Transport from a Borehole with Low Ph.

Water transport in textile factory

CMT La Laguna
Mexico

 | 

2018