Pexgol Elbow for Slurry Transport

Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE.

Case Study Nº

109

Customer

Antioquia Gold
Colombia

|

2022

Working Conditions

Fluid: Sludge | Temperature: 40°C / 104°F

Pexgol Pipes

Pexgol 45° elbow 160 mm, class 15 | GP flanged coupling 160 mm

Application

Slurry transport

Lenght

n/a

Categories

Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE

The Challenge

Antioquia Gold, a Colombian mining company, required continuous maintenance to the HDPE pipe (160 mm PN16) that they used for the discharge to the FALCON 1 gravimetric concentrator, which suffered from constant abrasion problems. It had to be thermo-fused in very short sections to give the necessary radius of curvature in the operation. This pipe had a durability of 1 to 2 months maximum.

Pexgol Solution

Due to its durability, ease of installation (mechanical) and because it does not require maintenance, Antioquia Gold decides to use a Pexgol elbow.

The elbow was installed and after 90 days of testing, the elbow and the connections have maintained hermeticity without fluid loss, maintaining the integrity and initial conditions during the period of operation, when subjected to the expected conditions.

Thanks to the benefits of Pexgol elbows and the versatility of the GP flange coupler, the tolerance of the elbow and its easy handling, the operation cuts were carried out satisfactorily. The elbow was installed by simply aligning the mechanical flanges, making the installation complete in 20 minutes.

Related Case Studies

Installation of Pexgol Pipes for Drainage of an Underground Mine

Vertical Drain in Underground Mine

Meridian Mine - Faena El Peñón
Chile

 | 

2018
Replacement of Carbon Steel Pipe for a Pexgol Pipe

Water Transportation

Cargill
Mexico

 | 

2017
Installation of Pexgol pipes for the transport of formation water (gas and minerals)

Gas Wells: Formation Water Treatment

Canacol
Colombia

 | 

2018
Transport of Concentrated Alcohol to 86% for the Production of Rum and Brandy

Transportation of Alcohol for the Production of Rum and Brandy

Cuba Ron
Cuba

 | 

2016
Food Transport Pexgol vs HDPE

Food Transport Pexgol vs HDPE

Marine Farms
Chile

 | 

2017
Replacement of a Drainage Line in an Underground Mine.

Drainage in Underground Mine

Atacama Kozan
Chile

 | 

2019