Potable Water Aqueduct

Transport of Drinking Water in Harsh Terrain.

Case Study Nº

80

Customer

Acueducto y Alcantarillado de Bogotá
Colombia

|

2019

Working Conditions

Pressure: 15 bar | Temperature: Ambient

Pexgol Pipes

Pexgol 110 mm (4”), class 15

Application

Potable Water Transport

Lenght

200 m / 656 ft

Categories

Transport of Drinking Water in Harsh Terrain.

The Challenge

The Bogotá Aqueduct and Sewer Company (Acueducto y Alcantarillado de Bogotá) needed to provide potable water to the Aguas Claras area (Colombia). This community is located on place that is very difficult to access due to the topography of the place. The pipe to be installed had to go through a mountainous and vegetated area.

Pexgol Solution

The client chose Pexgol due to its advantages, and theyt also wanted to carry out this installation as a test to compare the performance of the PE-X versus the HDPE that they regularly used.

The installation was carried out by deploying the pipe on the field, with no sand bed or need to be buried, being placed and dragged directly on the ground in just 4 hours.

After 180 days of successful operation, the Aqueduct and Sewerage System in Bogotá certified the good behavior of the installed pipeline and justified its use for the following reasons:

  • A 10-year guarantee was granted (for the transport of drinking water).
  • The pipes are designed for a lifespan of more than 50 years.
  • Easy manipulation in the field, which means fewer operators.
  • Minimize the use of accessories reducing costs, head losses, labor and installation time.
  • Due to its compatibility for connection with other pipes: HDPE, carbon steel, among others.

Related Case Studies

Water Extraction From Deep Wells (150 Meters)

Water Extraction from Wells

Andacollo Mine
Chile

 | 

2015
Potable Water Supply on Harsh Terrain

Potable Water Supply on Harsh Terrain

Mekorot / Beit Shemesh Water Company
Israel

 | 

2017
EMESA Optimizes Formation Water Transportation in Mendoza.

Pexgol’s Solution in Secondary Recovery for EMESA

EMESA
Argentina

 | 

2023
Transport of acid slurry at high temperatures

Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2012
Reducing maintenance and increasing safety in hydraulic backfill operations.

Pexgol Simplifies Slurry Transportation at Buriticá Mine

Zijin - Continental Gold
Colombia

 | 

2023
Reduced wear and increased durability in the sand cleaning process at KSB de México.

Improving efficiency in steel foundry with Pexgol

KSB de Mexico
Mexico

 | 

2023