Skip to content

Replacement of Steel Pipes for PE-X

Replacing Steel for PE-X Pipes to Transported Processed Water.

Case Study Nº

105

Customer

Rosebel Gold Mines – IamGold
Suriname

|

2020

Working Conditions

Pressure: 60 PSI | Flow: 70 m3/h | Temperature: 45°C | Fluid: Processed water

Pexgol Pipes

Pexgol 225 mm (8”)

Application

Processed water transportation

Lenght

100 m / 328 ft + elbows + tees + reducers

Categories

Replacing Steel for PE-X Pipes to Transported Processed Water.

The Challenge

At the Rosebel Gold mine they had serious scale problems in the water transport line for the SAG Fees Chute mill.

They generally used steel pipes that ended up becoming encrusted, which resulted in them needing to be cleaned and on many occasions changed in periods of 3 to 5 months. This generated losses in production and a large cost for the maintenance that the steel required. Additionally, in the periods of use, the pumping pressures had to increase since the internal diameter of the pipe was reduced.

Pexgol Solution

The client was aware of the advantages of Pexgol to prevent fouling in lime slurry transport applications and therefore it was decided to proceed with a first section for testing.

With the Pexgol piping system, which has a low internal roughness, long radius elbows and mechanical accessories were supplied that helped ensure that even between the joints there were no interferences.

Today the system has been working for more than 10 months without problems or fouling, which is already a success for the client since its installation is simple and the costs are lower than steel pipes.

The connections were mechanical, it was only necessary to cut the pipe to size and place screws. PE-X is much lighter than steel, so fitting it to the pipe racks was also simple.

Additionally, the plant has Victaulic-type connections on the steel pipes, which made the job simple as Pexgol can also connect with Victaulic.

Related Case Studies

In an engineering challenge, the Pexgol 225 mm (8”) Class 15 pipe proved to be the perfect solution for transporting tailings at the Mina Capela mining complex.

Environmental Protection and Efficiency in Tailings Management

Mina Capella - Grupo Peñoles
Mexico

 | 

2023
Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE.

Pexgol Elbow for Slurry Transport

Antioquia Gold
Colombia

 | 

2022
Dewatering tThrough Shafts for an Underground Lead-Zinc Mine.

Dewatering Through Shafts

Esan Eczacibasi Endustriyel Hammaddeler
Turkey

 | 

2019
Transportation of water in more than 150 mining crossroads

Water Transport on Crossroads

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2012
Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Pexgol’s chemical resistance and flexibility outperform HDPE in demanding leach pad operations.

Greater Efficiency and Safety in Leaching with Pexgol Pipes

Barrick Gold Corp.
Argentina

 | 

2025