Meltdown Water Transport

Pipe installation on a mountain

Case Study Nº

16

Customer

Codelco Andina, TADA 1-2 Project
Chile

|

2013

Working Conditions

Complex & harsh ground, 300 m altitude.

Pexgol Pipes

Pexgol 315 mm, Class 15 (SDR 11).

Application

Water transportation.

Lenght

3,300 m.

Categories

Pipe installation on a mountain

The Challenge

Codelco needed to transport meltdown water downhill at Andes Mountain range.

The water pipes installation was a big risk for the team, as well as huge workforce with short time schedules.

Pexgol Solution

Using hoses seemed to be the solution, but the complexity of its installation made the client decided to use Pexgol in long sections instead.

The installation was simplified by the use of Pexgol long sections.

The pipes were unrolled from it coils and jointed trough electro-fusion, to be dragged and mapped out according to the project.

The installation was done in perfect timing with an optimal performance.

Related Case Studies

Installation of Pexgol Pipe for the Transport of Abrasive Tailings.

Abrasive Tailings Transport

Pirquitas Mine
Argentina

 | 

2015
Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Transporting Brine at High Pressure

Mekorot
Israel

 | 

2020
Installation of Pexgol Pipes for Drainage in a Vertical Ground

Vertical Dewatering

Ferrexpo Poltava Mining
Ukraine

 | 

2019
High Pressure potable water line

High Pressure Potable Water Line

Antofagasta Minerals, Pelambres Mine
Chile

 | 

2014
Installation Oof Pexgol Pipes through a Chimney for Compressed Air.

Transport of Compressed Air for Underground Mine

HMC Gold
Chile

 | 

2021
Replacement of a HDPE Pipe for a Pexgol Pipe

Slurry Transportation

Sabinas Mine
Mexico

 | 

2017