Skip to content

Transport of Lime Slurry

Transport Of Lime Slurry At 100°C

Case Study Nº

28

Customer

Minas de Oro Nacional, Mulatos Mine
Mexico

|

2015

Working Conditions

Extreme transportation temperature (100°C).

Pexgol Pipes

Pexgol 90 mm (SDR 7.4).

Application

Lime slurry transportation.

Lenght

150 m.

Categories

Transport Of Lime Slurry At 100°C

The Challenge

The client needed to transport lime slurry, which is highly fouling due to the high temperatures and the liquid consistency. The lime slurry was transported at 100°C, damaging all metals and plastics that were not resistant enough. The fouling caused a considerable diminution on the inside diameter of the former pipe, sometimes even closing it completely. Previously the client used to work with a rubber hose, but due to the extreme conditions, and the lack of a flat inside surface, it wasn’t enough to prevent the accumulation.

Pexgol Solution

Golan provided 50 meters of Pexgol 90 mm pipe (3” – SDR 7.4). The installation was easy due to the one section pipe, that didn’t require joints. The natural curve radio was utilized to pass all the obstacles during the installation. Pexgol pipes proved to be the best solution, thanks to it’s high resistant to abrasion, corrosion, encrustation and resistance to high temperatures.

The client saved costs; formerly the rubber hose cost 6 times more than Pexgol. In the other hand, the MTBF was just two month.

Since the Pexgol pipe installation no maintenance has been required, not even plant stops.

Related Case Studies

Pipe installation on a mountain

Meltdown Water Transport

Codelco Andina, TADA 1-2 Project
Chile

 | 

2013
Grey Water Transportation

Recovered Water Transportation

Coeur Mexicana S.A. de C.V. Palmarejo
Mexico

 | 

2017
A Case Study on the Collaborative Engineering and Strategic Implementation of the Pexgol Pipeline System for Public Safety and Efficiency

Innovation in Safety: Pexgol Piping System for LPG Supply

Rawabi City
Israel

 | 

2010
Drainage in Underground Mine with Slopes Between 40° and 90°.

Water Drainage in Underground Mine

NEMISA Mine
Mexico

 | 

2018
Enhancing Efficiency and Durability in the Construction of Aerial Pipelines.

Facing the Challenges of the Neuquén Terrain in Argentina

Pluspetrol
Argentina

 | 

2023
850 Meters of Pipe Replaced in Less Than 24 Hours, Without Affecting Residents.

Goodbye Asbestos: Pexgol Modernizes Thermal Water Network

Raquet Club Lake Chapala
Mexico

 | 

2024