Transport of Silica Arena: HDPE vs Pexgol

Test Installation for Transporting Silica Sand.

Case Study Nº

90

Customer

Covia Corp
Mexico

|

2019

Working Conditions

Pneumatic transport at 6 bar

Pexgol Pipes

Pexgol Elbow 90° 225 mm (8”), Class 15 | Pexgol Flange Coupler 225 mm (8”)

Application

Transport of Silica Arena

Lenght

Categories

Test Installation for Transporting Silica Sand.

The Challenge

Covia Corp, a leading company in the manufacture and sale of industrial minerals in Mexico, required to pneumatic transport silica sand at 6 bar (with 50% solids). Initially they worked with 225mm (8”) HDPE pipes that suffered from high levels of wear at the elbows due to abrasion of the material it was carrying.

Pexgol Solution

The client decided to replace one of the HDPE elbows with a Pexgol 90° 225 mm (8”) class 15 and test it for 3 months.
HDPE elbows generally lasted up to a month and a half of work. The Pexgol elbow had to at least double the operating time to pass the test.

After 3 months of testing it was shown that Pexgol exceeded expectations. It’s been more than a year and the elbows continue to function without problems.

Only torque wrenches were used for the installation.

Related Case Studies

Optimization of Water Systems in the Energy Industry.

“Threading” Pexgol Pipes

Pluspetrol
Argentina

 | 

2023
Scale build up reduction - highly concentrated lime solution

Process Water – Brine Transportation

SQM Nueva Victoria-Iquique
Chile

 | 

2010
Water line feed from wells to mine

Mine Dewatering – High Pressure Conditions

Antofagasta Minerals, Michilla Mine
Chile

 | 

2011
Water line feed from wells to mine

Water Lines – High Pressure Water Feed Lines

Yamana Gold, Meridian Mine
Chile

 | 

2012
Test Of Pexgol Pipes Vs Hdpe Pipes For Brine Transportation

Test: Pexgol vs HDPE for Brine Transportation

YBL
Bolivia

 | 

2017
EMESA Optimizes Formation Water Transportation in Mendoza.

Pexgol’s Solution in Secondary Recovery for EMESA

EMESA
Argentina

 | 

2023