Transportation of Ore Slurry

Replacing steel pipes suffering from sediment formation

Case Study Nº

10

Customer

RUSAL, aluminum factory
Russia

|

2012

Working Conditions

Specific gravity was 1.510-1.550 kg/l, pressure 2 Bar (maximum 3-4 Bar), temperature of 99°C. Chemical composition: Na2O, AI2O3, F32O3, SiO2, CaO. Flow rate: 180M3/H.

Pexgol Pipes

160 mm class 15 (SDR 11).

Application

Industrial.

Lenght

15 meters with flared ends

Categories

Transportation of Ore Slurry

The Challenge

The main challenges were corrosion and scaling formation on the inner surface of existing steel pipes, causing a decrease of inner diameter of the pipes and consequent decrease of their throughput ability.

Pexgol Solution

Replacement of the existing 159 mm steel pipe with a 160 mm class 15 (SDR 11) Pexgol pipe.

The test line consists of three parts: One section is a white G-Pex pipe manufactured in Moscow, approximately 12 m long. Two more sections are 0.5 m long, each of black Pexgol pipe with flared ends, manufactured in Golan Plastic Products, Israel. These sections were connected by Plasson’s

Electro-fusion Pex-2-Pex couplers. During the entire operation the pipe was under continuous vibration because of a grinder operation.

The pipe was installed by the field team of Polimerteplo Group Llc accompanied by the field installation engineer of Gloan Plastic Products Ltd.

Related Case Studies

Pexgol: Delivering Rapid, Reliable & Long-lasting Mining Drainage Solutions

Addressing Drainage Challenges with Pexgol

Avino Mine
Mexico

 | 

2023
Pan American Energy implements an efficient and sustainable solution for brine transportation.

Fast and Safe Brine Transport in the Salar de Hombre Muerto

Lithos (PAE)
Argentina

 | 

2024
Work with High Pressures and Extreme Ambient Temperature

Water Transport in Copper Mine

Zaldivar SPA Mine
Chile

 | 

2018
Improving the efficiency of salmon farming with the superior solution of Pexgol pipes.

Pexgol’s Pipe Solution Enhances Salmon Farming

Mowi
Chile

 | 

2021
Enhancing Efficiency and Durability in the Construction of Aerial Pipelines.

Facing the Challenges of the Neuquén Terrain in Argentina

Pluspetrol
Argentina

 | 

2023
Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

Pumping Mining Effluents

AngloGold Ashanti
Brazil

 | 

2019