Skip to content

Vertical Dewatering

Installation of Pexgol Pipes for Drainage in a Vertical Ground

Case Study Nº

69

Customer

Ferrexpo Poltava Mining
Ukraine

|

2019

Working Conditions

Vertical installation | Ambient temperature: -30°C to 40°C / -22°F to 104°F

Pexgol Pipes

Pexgol 315 mm (12”), class 30 | Pexgol 315 mm (12”), class 24 | Pexgol 315 mm (12”), class 19 | Pexgol 280 mm (10”), class 10

Application

Mine Dewatering

Lenght

2700 m

Categories

Installation of Pexgol Pipes for Drainage in a Vertical Ground

The Challenge

Ferrexpo Poltava Mining required the installation of pipeline for mine dewatering to be installed vertically from the bottom of the quarry to its surface. The pipe needed to be resistant to cracks and be provided in long sections in order to avoid many joints.

Pexgol Solution

The client decided to install Pexgol pipes with OD 315 mm (12”) with 30, 24 and 19 class in coils by 90 and 120 m each for most difficult areas where the pressure varied from 32 to 15 bars. At the end of the line Pexgol OD 280 mm (10”), class 10 pipes were used in straight sections of 11.8 m.
All the pipes were connected by electrofusion couplers. In the places with high pressure were also used reinforcements for a safe installation.

A Caterpillar D10T bulldozer and the 40 ton excavator was used for unwinding the coils on core. Then the pipe were dropped from the top by the bulldozer & excavator. All connections were made with the electrofusion couplers. In the most difficult areas were also used reinforcements and fixpoint bridges.

Related Case Studies

Enhanced hydraulic and structural reliability for critical community infrastructure.

Optimization of Potable Water Supply for 1,600 residents

Rincón de la Candelaria
Mexico

 | 

2025
Guaranteeing an efficient water supply with the Pexgol piping solution in the Mendoza-San Juan Highway project.

Streamlining Water Supply in Highway Construction

Chediack / Ceosa
Argentina

 | 

2023
Installation of Pexgol Pipe to Transport Fiber Optic Cables.

Fiber Optic Cables Through a Vertical Shaft

Sinohydro
Israel

 | 

2021
Transport of Formation Water with Hydrocarbons.

Formation Water Transport

ROCH
Argentina

 | 

2015
Installation of Pexgol pipes for the transport of formation water (gas and minerals)

Gas Wells: Formation Water Treatment

Canacol
Colombia

 | 

2018
Pexgol Pipe Installation for Open Pit Mine Drainage.

High Pressure Dewatering in Open Pit Mine

Lundin Mining
Chile

 | 

2021