Water Lines – High Pressure Water Feed Lines

Water line feed from wells to mine

Case Study Nº

5

Customer

Yamana Gold, Meridian Mine
Chile

|

2012

Working Conditions

High pressure (over 24 bar), corrosion and ambient temperature at 40°C/104°F. The first 2,750 meters of pipes were covered in sand, the last 2,750 meters were exposed to the sun.

Pexgol Pipes

Pexgol 225×30.8, Class 24.

Application

Dewatering.

Lenght

5,500 meters.

Categories

Water Lines – High Pressure Water Feed Lines

The Challenge

The high pressure and corrosion caused constant failure of the two initial parallel steel pipelines and serious threats to the production process.

One steel pipeline was out of service for at least two years and the other suffered from severe corrosion. Since this was the only main line transporting water to the production line, it was critical for the whole production process. The client required a highly durable and a quick install solution for non-stop performance

Pexgol Solution

The replacement of the steel pipeline with Pexgol’s flexible and high resistance to corrosion pipe solution eliminated previous failures. In addition, Pexgol supplied easy-to-install longer pipes.

The client is so pleased with the solution that he will be replacing the HDPE pipes that are part of this line as well.

Related Case Studies

Pexgol Pipe for the Transport of Fluorosilicic Acid.

Fluorosilicic Acid Transport

Phosphate Mine – ICL Rotem
Israel

 | 

1995
Transport of Muddy Water (Pome) witha High Content of Organic Load.

Transport of Muddy Water in a Palm Oil Processing Plant

La Gloria
Colombia

 | 

2020
Pexgol’s resistance to scaling and chemicals delivers consistent operation in open-pit mining.

Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

Buena Vista del Cobre
Mexico

 | 

2024
The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Improvement in Brine Management through Pexgol Piping

Sales de Jujuy
Argentina

 | 

2023
Test Installation for Transporting Silica Sand.

Transport of Silica Arena: HDPE vs Pexgol

Covia Corp
Mexico

 | 

2019
Water Extraction From A Middle Pool To The Exterior Of The Mine

Dewatering at an Open Cast Mine

Codelco, Ministro Hales Division
Chile

 | 

2016